This update outlines the progress of the SIS project from July 26, 2006, detailing the design phase and preparatory projects scheduled from April 24 to August 4. Key implementation steps include migrating ATMs to RPR over the first 11 weeks post-Labor Day and subsequent migrations leading to K12 and State systems completion. Although there are current risks with DCN power installation, all necessary equipment has been received, and testing will finish before implementation. Next IVN sessions and resources for more information are provided.
E N D
SIS 2006 Update July 26, 2006
Big Picture • Design Phase • Preparatory Projects Phase – April 24 – August 4 • Configuration Documentation & Testing • Site preps • Implementation – Shortly after Labor Day
Implementation • Weeks 1 – 3 – Test & Migrate Bismarck-Fargo ATMs to RPR • Week 4 & 5 – Burn-in time for RPR, Prep for PSD migration • Week 6 & 7 – Migrate PSD • Week 8 & 9 – Migrate I2 and prep for K12 • Week 10 & 11 – Migrate K12 • Week 12 - 15 – Migrate K12 Video • Week 16 - 18 – Prep & Migrate State • Weeks 19 – 21 – Prep & Migrate HE
Current Risks/Issues • DCN power not installed as scheduled
Good News • All of the equipment ordered has arrived • Configuration & testing is will be complete before implementation. • Video migration underway • Still believe we can complete by the end of the calendar year.
More Information • Next IVN Session = August 30 • www.stagenet.nd.gov/projects/infrastructure/index.html • Biweekly status reports • Presentations • Dirk Huggett • dhuggett@nd.gov • 701-223-2248