1 / 11

Load Requirements vs Resources

This report, commissioned by ISO-NE and authored by Ken Bekman, analyzes the levelized cost for simple cycle gas turbines based on data from 1999 to 2001. It reflects an assumed capital cost of $413/KW, resulting in a levelized margin requirement of $74/KW-yr (excluding fuel). Analysis of the top 500 hours highlights remarkably consistent results: $528/MWh in 1999, $538/MWh in 2000, and $532/MWh in 2001. The findings suggest that while the cost of new peakers is relatively low, high operational revenue requirements and market constraints pose challenges.

daria
Télécharger la présentation

Load Requirements vs Resources

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Load Requirements vs Resources Energy Infrastructure Conference January 23-25, 2002 Ken Bekman

  2. What is the Levelized Cost for a Simple Cycle Gas Turbine • E-Acumen commissioned by ISO-NE • Report issued on December 10 • Assumed Capital Cost of $413/Kw • Considered low based on CEE experience • Results in levelized margin requirement of $74/Kw-yr (not including fuel)

  3. Analysis of Top 500 Hours 1999 thru 2001 • Assumptions • All energy requirements filled by Peakers • Peakers have no other source of revenue • All peaking energy suppliers share in revenue equally

  4. Analysis of Top 500 Hours 1999 thru 2001 • Calculation Method • Integrated Hourly Energy Requirement for top 500 Hours (Delivered Energy) • Calculated Delta between Peak Load and Load at 500th Hour in MWs. (Capacity Requirement) • Applied the following Equation • $/MWHr = Capacity Requirement*$74,000 Delivered Energy

  5. Analysis of Top 500 Hours all 1999 thru 2001 • Results - Remarkably Consistent • 1999 $528/MWHr + Fuel • 2000 $538/MWHr + Fuel • 2001 $532/MWHr + Fuel

  6. Analysis of Incremental Energy Requirement for 2001 • Methodology Similar to Top 500 Hrs • Only Looked at Incremental Energy Requirement above 1999 Peak • $2350/MWHr + Fuel required to support Incremental Peaker

  7. What Does It All Mean • Cost of New Peaker is relatively low • $700/KW for Base load combined cycle • $500/KW for Peaking Unit • Capacity Factor Very Poor • Very high revenue requirement per hour of operation • Capped energy prices and lack of viable I’Cap market may make revenue unattainable

More Related