An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MidMAN3 Rollout Neil Shewry JANET(UK) MidMAN3 Project Manager

  2. Overview • Current status • Immediate next steps • Rollout process • SJ5 connectivity • Rollout timetable • Migration process • Issues to consider

  3. Current status (1) • Contract awarded to NTL:Telewest • Negotiations ongoing……

  4. Current status (2) • JANET(UK) Project Manager assigned • Yours truly! • Senior JANET NOC engineer assigned • Tony Hacche • NTL:Telewest Project Manager assigned • Jim Offord • JANET(UK) Project Board • Bob Day, CTO • Rolly Trice, Regional Delivery Group Manager • Tim Kidd, Head of Operations

  5. Immediate Next Steps • Get the contract signed! • Site surveys • NTL • BT • JSD to contact all sites • NTL:Telewest to begin ordering circuits • JANET(UK) to order IP routing equipment

  6. Rollout Process • Rollout beginning imminently • MidMAN3 network to be RFS by end of June 2008 • JANET(UK) and NTL:Telewest activities to take place concurrently • Weekly progress meetings • Regular updates to MidMAN sites

  7. SJ5 Connectivity • 2.5G to Warwick RNEP • 2.5G to Birmingham RNEP

  8. SJ5 Connectivity • 2.5G to Warwick RNEP • 2.5G to Birmingham RNEP • 10G links to MM3 – already present • PICs for core routers on order

  9. SJ5 Connectivity • 2.5G to Warwick RNEP • 2.5G to Birmingham RNEP • 10G links to MM3 – already present • PICs for core routers on order • New JANET router at each RNEP

  10. SJ5 Connectivity • 2.5G to Warwick RNEP • 2.5G to Birmingham RNEP • 10G links to MM3 – already present • PICs for core routers on order • New JANET router at each RNEP • Build MM3 alongside MM2 • Routing between MM3 & MM3 across SJ5

  11. SJ5 Connectivity • 2.5G to Warwick RNEP • 2.5G to Birmingham RNEP • 10G links to MM3 – already present • PICs for core routers on order • New JANET router at each RNEP • Build MM3 alongside MM2 • Routing between MM3 & MM3 across SJ5 • Decommission MM2 when migration complete

  12. Rollout Timetable

  13. Migration process (1) • MM3 due for completion 30th June 2008 • MM2 -> MM3 migration to be completed by end of September 2008 • Tuesday morning maintenance periods used for site migrations • Every 3rd Tuesday as contingency • Circuits to be tested & connected up as they become available

  14. Migration process (2) • Specific migration schedule to be produced at a later date • This schedule may be subject to change as the rollout progresses

  15. Migration process (2) • Specific migration schedule to be produced at a later date • This schedule may be subject to change as the rollout progresses • It may be necessary to use Thursday mornings

  16. Migration process (2) • Specific migration schedule to be produced at a later date • This schedule may be subject to change as the rollout progresses • It may be necessary to use Thursday mornings • Weekend/evening slots are not on the agenda

  17. Issues to consider • JANET managed routers • Clearing: 14/8 to 14/9 (ish)

  18. Issues to consider • JANET managed routers • Clearing: 14/8 to 14/9 (ish) • JANET(UK) reserves the right to migrate sites during the clearing period

  19. Issues to consider • JANET managed routers • Clearing: 14/8 to 14/9 (ish) • JANET(UK) reserves the right to migrate sites during the clearing period • Anything else ??

  20. Contact Details • MidMAN3 Project Manager • Neil Shewry • Neil.Shewry@ja.net • 01235 822375 • JANET Service Desk • Service@ja.net • 0870 850 2212