An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Concrete removal Concrete cutting area shrink wrapped to prevent dust. Concrete cutting starts Tuesday 25th March, approx 4 - 6 weeks.

  2. South and North Magnetic steel walls • Steel tender awarded Tuesday 25th March (OJEC requires a 10 day period to give unsuccessful tenders the right to appeal). • 3D model of shield walls to • Label the steel plates for ease of installation. • identify plates in each staged delivery. • Make sure everything fits together.

  3. False Floor Provisional design from contactor

  4. False floor • False floor in 3 sections • Frame (brown) • Cover plates (red) • Intermediate piece (green)

  5. False floor intermediate piece Hole pattern is either done in one plate (one size fits all, shown here) or in several modular plates to suit each stage of the build.