Congestion Management Work Group Update

Congestion Management Work Group Update. For WMS 3-18-09 Marguerite Wagner, PSEG Texas. Topics Discussed. Business Process for Adjusting TTC for TCR auctions Singleton Outage San Angelo – Menard NOGRR 25. TCR Determination: # of TCRs for Auction.

devlin
Télécharger la présentation

Congestion Management Work Group Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Congestion Management Work Group Update For WMS 3-18-09 Marguerite Wagner, PSEG Texas

  2. Topics Discussed • Business Process for Adjusting TTC for TCR auctions • Singleton Outage • San Angelo – Menard • NOGRR 25

  3. TCR Determination: # of TCRs for Auction • Protocols 7.5.3.1 provide ERCOT with authority to adjust # of TCRs for sale • “…in determining the amount of TCRs available in each monthly auction, ERCOT shall seek to achieve revenue neutrality and avoid a revenue shortfall due to payment to TCR holders for the month.” • ERCOT Proposal: Congestion Costs + TCR Revenues – TCR Payment = 0 • CMWG Discussion – Auction Revenues should not be considered in the revenue neutrality evaluation • One alternate proposal discussed at CMWG: Congestion costs + TCR revenues for oversold #TCRs only - TCR payments = 0

  4. TCR Determination: Questions for WMS • Should ERCOT adjust number of TCRs for sale in monthly? • Affects ability to hedge ‘prompt month’ • Historical Congestion Rents Not Sufficient to Cover Pay Out • Due to difficulty to forecast avail Transmission Capability in RT • Should improve with longer lead times for Outage Submission

  5. Singleton Substation Construction • ERCOT presented outline outages being taken to allow construction of Singleton Sub • 3/20 – 4/9: various coincidental outages of Tomball-Jewett configurations • Since then ERCOT determination to implement “conditional” NH CREs • Peters to Flewellen 138kV line and the Tomball to Hockley 138kV line as CREs Houston

  6. San Angelo - Menard • Issue identified by IMM • ERCOT discussed potential CRE—but line currently outaged—delaying request • Significant OOMing for control • Potential 2010 CSC? • Stay tuned San Angelo

  7. Upcoming Work Items for CMWG • CREs • Do we need refinement in protocols about PTDF effectiveness before 2010 CSC determination? • Last year were guided by 3%/5% • Balance ERCOT/Market use/understanding of “conditional” CREs • Nodal • CCT • NOGRR 25

  8. NOGRR 25 – OWG Request to CMWG Develop Metrics for Nodal Protocols • 9.12.4(a)8.2(2)(d)Three consecutive days of a particular congestion constraint (constraints passed to Security-Constrained Economic Dispatch (SCED) from Network Security Analysis (NSA)) in Real-Time not identified in the Day Ahead Market (DAM); • 9.12.4(b)8.2(2)(d)Two consecutive hours of a particular congestion constraint in Real-Time not identified in the Hourly Reliability Unit Commitment (HRUC) process; • 9.12.4(c)8.2(2)(d)Two consecutive days of a particular congestion constraint in Real-Time not identified in the Day-Ahead Reliability Unit Commitment (DRUC) process.