1 / 11

LCLS Control System Controls Organization Overview A Progress Report Hamid Shoaee

LCLS Control System Controls Organization Overview A Progress Report Hamid Shoaee. Engineering Production Challenges. Earlier this year in response to concerns about Controls readiness for installation, engineering teams were formed to address design, integration and production issues

doctor
Télécharger la présentation

LCLS Control System Controls Organization Overview A Progress Report Hamid Shoaee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Control SystemControls Organization OverviewA Progress ReportHamid Shoaee

  2. Engineering Production Challenges • Earlier this year in response to concerns about Controls readiness for installation, engineering teams were formed to address design, integration and production issues • Some specific concerns… • Lagging procurement, indicating slow progress in a number of areas, threatening injector commissioning • Some activities such as cable plant design were as much as 6 months behind the schedule

  3. Control System Integration • Some specific concerns… • While we are generally successful in designing a system, difficulties were experienced in the production stages leading to the field installation • Lack of sufficient technical expertise in a number of areas, particularly in electronics hardware engineering • Lack of sufficient personnel to complete the product lifecycle particularly in the areas of coordination, design, documents, fabrication and installation • Integration issues, both within controls as well as with other LCLS systems

  4. LCLS Engineering Teams • The goals for the Engineering Teams were: • Multi-disciplinary teams to managing the full product lifecycle from specification and design to engineering development, production, installation and commissioning • To ensure communication among all disciplines, and that all interface issues are addressed • Each team has representatives from Controls, CPE, Mechanical Systems, Physics, CF, etc. • There will be an integrated project meeting for each subsystem with all the relevant disciplines represented

  5. LCLS Controls Engineering Teams • Team activities have included: • Developing a schedule covering all phases leading to installation and commissioning • Production of appropriate documents (ESD, ICD, etc.) and design reviews • Interfacing with Mario Ortega, Mike DiSalvo and Bob Fuller to coordinate procurement • Interfacing with various shops to complete the back-end of the project leading to field installation

  6. LCLS Controls Engineering Teams • Safety Systems • PPS • Bong, Fitch, J. Brown, Saleski • Laser Safety • Bong, Fitch, Brown, Gilevich, Bill White, Saleski • Beam Stoppers (PPS) • Bong, Roster, V. Brown, Langton • MPS • Norum, Alarcon, Tilghman, Browne • Toroids Ion chambers, PLIC, limit switches • Norum, B. Bennett, Simmons, Traeger, Montagne • BCS • Alarcon, Bennett, Simmons Traeger, Saleski, Montagne

  7. LCLS Controls Engineering Teams • Beam Instrumentation and Diagnostics • BPMs (stripline type) • Straumann, Smith, Johnson, Medvedko, V. Smith • Toroids • Cecere, S. Smith, Browne, Peng, Montagne, Dowell • Profile monitors, OTR, YAG, etc. • Peng, Roster, V. Brown, Montagne, D. Martin, Loos • Faraday cup • Cecere, Roster, V. Brown, Rago • Bunch length monitor • Peng, Frisch, S. Smith, Borden, Wu

  8. LCLS Controls Engineering Teams • Global Controls • Timing System • Allison, Akre, Browne, D. Brown, Dusatko, White, Lewis • LLRF • Akre, Kotturi, Olsen, Dusatko, Browne • Mover systems (wire scanners, BC1, collimators, tune-up dump) • Murray, Porter, J. Bong, Tilghman, Langton, Montagne (collimators), Krejcik • Vacuum system • Schuh, Porter, O’Neal L. Eriksson, S. Lewis • Data communications and networks • Lahey (& team), Murray, Hooker& Granieri (SCCS)

  9. LCLS Controls Engineering Teams • High level applications, Feedback systems • Fairley, Rogind, Zelazny, Chevtsov, Allison • Power supplies • Luchini, Bellomo, MacNair, DeLira, Rogind, R. Carr, • Laser controls (cameras, motion control, insertion) • Peng, White, Roster, Yee, V. Brown, Dowell, Miahnahri • Laser Heater – Controls • Peng, White, Roster, Yee, R. Carr, Miahnahri • Temperature monitoring & control • Schuh, Tilghman, Nguyen, Dowell, Emma, Cutino • General signal distribution (cables plant, racks, crates, patch panels, etc.) • Ortega, Tilghman, S. Nguyen

  10. Engineering Teams – Progress Report • The engineering team approach has been a success in addressing the issues that prevented us from proceeding from design to successful installation • Successes… • More awareness of the production issues such as design documents, wiring diagrams, fabrication, shop orders, etc. • Production issues are increasingly handled within teams • Opportunities… • Interface issues – “Controls” is every where, however the teams are not always included in system discussions in other departments • Insufficient number of coordinators, designers, electricians, etc. to serve all the teams • The production “shops” are over loaded • Not all the teams are self-sufficient enough to complete their systems independently.

  11. Summary – The integration of LCLS Controls with SLAC has been a success • Our “production” issues have been addressed and to some extent solve, but opportunities exist • We are in a much better position to proceed with the rest of the project, linac, undulator, etc. • Controls integration has been vital in completing our projects • We need to “staff up” in key production areas to have a smoother installation phase in the future

More Related