1 / 35

Control System Overview April 16, 2007 Hamid Shoaee for the LCLS Controls Group

Control System Overview April 16, 2007 Hamid Shoaee for the LCLS Controls Group. Outline Injector control system installation & commissioning Status update Linac & beyond Summary. Accomplishments in the past six months.

oprah
Télécharger la présentation

Control System Overview April 16, 2007 Hamid Shoaee for the LCLS Controls Group

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Control System OverviewApril 16, 2007Hamid Shoaeefor theLCLS Controls Group Outline • Injector control system installation & commissioning • Status update • Linac & beyond • Summary

  2. Accomplishments in the past six months • Field installation of large amount of cable plant, networking, racks, electronics and software for injector control • Development of detailed plans for linac and BC2 installation • Coordination and re-planning of undulator control with ANL • Development of a conceptual design for X-ray End Stations DAQ and Controls • AIP projects for MCC networks upgrade, LCLS MPS and Linac BPM • Starting the design of next generation applications software

  3. The main focus in the past six months has been the installation and commissioning of the injector Controls • Installation of the cable plant including trays, long haul DC and I&C cables, terminations, etc. • Phase 1 (Apr. ’06 thru Jun. ’06) • Phase II (Aug. ’06 thru Dec. ’06, including Christmas holidays) • Final terminations were occasionally delayed pending mechanical installations • Installation of the electronics racks, loading of crates, electronics chassis, modules, and intra-rack wiring • Installation of the Controls software on the front-end computers (IOC) and production servers

  4. Phase II Installation Scope - Gun to TD11

  5. MCC, Networks, Servers, & Workstations • Production Systems Delivered • Networks at S20 RF Hut & MCC: physical and wireless • LCLSDMZ, LCLS private, wireless • MCC infrastructure upgrade: power & racks • LINUX Servers for applications and EPICS data archiving • Control Room Linux Workstation • MCC and S20 Laser Room are actively in use for commissioning

  6. Main Control Center is in full operation

  7. All LCLS Safety Systems Are Operational • Laser Safety System (LSS) • Was needed early to allow laser commissioning • PPS • Passed many reviews by internal and external reviewers, citizens committees • The FIRST SLAC programmable PPS is online and operational • BCS • Prevents radiation from ‘escaping’ the shielding enclosure • Direct measurements of radiation or beam loss • Protection of safety-critical collimators and stoppers • The need for BCS was identified late, and the system had an aggressive schedule, but was completed and certified in time for ARR approval

  8. Safety Systems – MPS • Interim MPS • Using existing linac infrastructure (1553 MPS) • Adding new signals and devices for LCLS • Interim MPS will be used for gating beam • Single Shot Mode • Burst Mode • Pockels cell and MPS mechanical shutter limit laser rate on cathode • LCLS MPS (presentation at break out) • Will be used to protect the undulator and photon sections • Held conceptual design review, now proceeding to detailed design

  9. Cable Plant, Racks, etc. Networking MCC infrastructure Magnet power supply Vacuum Controls LLRF Timing Laser control Laser alignment OTR/YAG image acquisition BPM Toroid Wire Scanners Faraday Cup Cerenkov monitor Moveable collimator BC1 beamline control Bunch length monitor LSS PPS MPS BCS Gun Temp stabilization Image management Online Models MATLAB interface Controls Sub-Systems installed

  10. …and arriving soon • BPM acquisition through SCP (SLC-AWARE IOC) • Orbit fitting

  11. Schuh Norum LCLS Controls Home Screen

  12. Graphical displays help with identifying components

  13. Magnet Controls

  14. Magnet software tested & in production

  15. Vacuum System has been in operation over one month with signal in data archiving

  16. Wire Scanner Control D. Murray

  17. Movable Beamlinesuccessfully exercised this weekend

  18. Injector LLRF Work Completed R. AkreD. Kotturi • Linac Sector 0 RF Upgrade • All 3 RF Chassis completed and Installed • Sector 20 RF distribution system - • Phase and Amplitude Controllers (SPAC) - Operational • Phase and Amplitude Detectors (PAD) - Operational • Phased Locked Oscillator – Use SPPS unit for Turn On • LO Generator - Operational • Multiplier – 476MHz to 2856MHz - Operational • 4 distribution chassis - Operational • LLRF Control and Monitor System • 1 kW Solid State S-Band Amplifiers – 5 units • PADs – 6 Klystron units in Fabrication • PADs – Gun, L0A, L0B, L1S –Operational • PACs – Gun, L0A, L0B, L1S –Operational • Beam Phase Cavity • Pill box cavity with 2 probes and 4 tuners – Complete

  19. Operational Phase & Amplitude Detectors • S-Band Ref System • Laser • Gun • L0 (A&B) • L1-S

  20. Operational Phase & Amplitude Controllers • S-Band Reference System • Laser • Gun • L0-A • L0-B • L1-S

  21. Monitoring front end computers (IOC)

  22. Injection Laser Control System • The injector laser stabilization system includes two feedback loops • The first loop includes two mirrors, each with two actuators and one camera. It stabilizes laser traveling through a 10-meter tube • The second loop includes one mirror with two actuators and adjusts the laser position on the cathode. • The IOC reads the image from camera, calculates the laser’s position error and applies a correction to the actuators. • The loop operates @ 1 Hz, and the camera is synced to 120Hz.

  23. Timing System Break out talk Linac main drive line ~ FIDO 119 MHz 360 Hz SLC MPG I O C P N E T E V G LCLS events SLC events • LCLS Digitizer • LLRF • BPMs • Toroids • Cameras • GADCs • Old klystrons I O C E V R TTL m P P N E T S T B TTL-NIM convert. SLC Trigs

  24. Timing System Progress since October, 2006 • Completed Installation in sectors 20 and 21 • Commissioning is in progress • Finished hardware bench testing • Finished PMC-EVR driver • EVG sequence RAM programming at 360Hz • Timestamp distribution on the EVR IOCs • Completed cabling plans and documentation • Completed beam-synchronous acquisition

  25. The injector design optics model is now available online

  26. MCC Applications & Infrastructure • Configuration management (save & restore) • Alarm management • Error Logs • Data archiving • Correlations plot • Buffeted acquisition • Online model • Artemis problem tracking • Operations and Physics E-logs • The SLC-aware IOC provides beam synchronous data to Buffered Acquisition and Correlation Plots from a number of sources • AIP network upgrade at MCC for gigabit traffic to support digital control room

  27. Image Management Bunch Length Measurement Emittance and Energy Application Applications provided in MATLAB

  28. Linac & BC2 Controls Installation (Fall ‘07) • BC2 installation, similar scope to BC1 • Very little engineering development • The biggest challenge is meeting the schedule • The scope includes • Extending the new timing system • Safety systems (MPS, BCS) • Adding new magnets including pulsed horizontal dipole magnet • Adding BPM, x-collimator, OTR screen • BPM electronics upgraded (resolution improved)

  29. Linac & BC2 Controls Installation Schedule Overview: Controls ready 12/3/2007

  30. X-Ray End Station DAQ & Controls (Presentation at controls breakout) • Developed a conceptual design for end station data acquisition and control • Held a Conceptual Design Review • Developed a detailed task list and a project plan • The AMOS experiment may eventually take data @120Hz producing ~700 MB/second or 2.4 TB/hour or ~58 TB/24 hour • The plan is to build on previous experience. • Initially use commercial digitizer and COTS CPU for spectrometer data. • Use scalable technology developed for LSST for CCD data. • Capitalize on years of BaBar experience with hierarchical storage and management of HEP data. • ~1 TB/day raw data. • ~1 TB/day derived data. • ~1.5 PB total Babar data. • Extend/integrate several SLAC-developed Java-based technologies for data retrieval and analysis.

  31. XES Detail – Data Acquisition 1. Channel Access (Ethernet) 3. EVR (Fiber) 2. Beam Line 120 Hz Data 6. DAQ Data to SCCS 5. SLAC WAN (Ethernet) 4. MPS (Reflective Memory Fiber) XES Hutch XES private subnet 2 Detector Types 2 DAQ Types EELOG Spectrometer SBC DAQ XES Controller D PC Non-RTOS A TOF/Momentum Instrument cPCI ADC RTOS 1 Gb E 1 Gb E 5 G Spectrometer Monitor 1 Gb E Visual Data Monitor EPICS Config PVs XES Data Cache PC Non-RTOS 1 Gb E 1 Gb E 1 Gb E 6 CCD Pixel Detector CE Module DAQ Beam Line Processor PPC RTOS B E SBC RTOS Front End Board Fast Serial FPGA F 1 Gb E MPS PMC 4 G CCD Monitor 1 Gb E EVR VME 3 EPICS Config PVs Beam Line Data PMC 1 Gb E C 2 1 Gb E 10 Gb Enet Channel Access Gateway Experiment Chamber 1 A. EPICS & Local Control (Hutch Subnet) B. Distributed EVR Hardware Triggers C. Beam Line & Timestamp Data (dedicated Enet) D. ADC Control & Digitized Data G. Visual Monitor Data E. Detector Control & Digitized Data F. DAQ Data to Cache

  32. Plans for the Next Six Months • Complete the majority of Linac BC2 installation • Develop detailed plans for LTU, Undulator installation • Complete the design of XES controls, DAQ and data management • Complete AIP projects • Detailed design for next generation high level applications

  33. Breakout Session 4 – CONTROLSLocation – Redwood A, Bldg 48 Monday, April 16th • Time Topic Presenter • 1:30pm Controls commissioning experience P. Krejcik • 2:00pm LCLS MPS S. Norum • 2:30pm BPM and Toroid Update S. Smith • 3:00pm Break • 3:30pm X-ray End Station (XES) Controls R. Sass • 4:00pm Timing Systems update S. Allison • 4:30pm BC2/Linac Controls Installation Planning H. Shoaee • 5:00pm Discussion Tuesday, April 17th • 8:00am MATLAB Applications Software M. Zelazny

  34. Conclusions • The injector control system is online & operational • It has taken heroic effort by Controls group to meet the commissioning deadline • The plans are in place for linac & BC2 installation • We have developed a detailed plan for the undulator control in collaboration with ANL • A conceptual design is in place for X-ray End Station data acquisition and control • The major risk for the above items is schedule rather than technical complexity

More Related