1 / 11

Summary project outline

Summary project outline. WEBSITE CREATION OF CMTU. Project title: Website creation of CMTU Duration: 18 months Starting date(indicative): 01/01/2003 Project language: Mongolia Preparation date 22/08/2002 Author Bolormaa Rentsendorj. Background and Justification.

dominy
Télécharger la présentation

Summary project outline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Summary project outline WEBSITE CREATION OF CMTU

  2. Project title: Website creation of CMTU Duration:18 months Starting date(indicative):01/01/2003 Project language:Mongolia Preparation date22/08/2002 AuthorBolormaa Rentsendorj

  3. Background and Justification Using Internet is becoming purt of everyday activities all of the world. Accordingly (so) most people of our country need Trade Union information. But we don’t have website. Therefore our Trade Union necessary created website.

  4. Target Groups This work plan is meant for: 5 Mongolian Trade Union members and leader

  5. Development objectives This work plan will contribute to: Modernising the communication systems of CMTU Using the mailing list and exchange information. Providing important information and publications about the present labour situations in the country and in the world.

  6. Immediate objectives Creating a website of the CMTU (5 participants will create a website) Spreading information about Mongolian labour issues to other organisations Establishing better communication among the members

  7. Indicators of achievement In the website one day how many people using

  8. Activities Select 5 staff from national centre and other experts organisation and form a website development team Training on website creation 2 weeks Designing of website Seeking approval from the Executive Opening of the website and publicise it Creating a website

  9. Inputs Computer One Scanner One Printer Telephone line + bill Internet connection One Digital camera Papers Total cost4,000 $

  10. Monitoring Reporting and Evaluation Along with me one computer expert well be required to carry out the technical tasks, supervision and monitoring of the project. To monitor the development of the project a supervisory committee will be formed.

  11. Thank you!

More Related