This document outlines the Tentative HIAPER Development Plan and the projected integration schedule from October 2004 to September 2008. Key phases include critical infrastructure development, pilot proficiency training, and progressive science uploads and research. The plan details sequential infrastructure upgrade packages and integration schedules for advanced scientific instruments. By September 2008, essential instruments for atmospheric research will include cloud radar, aerosol mass spectrometers, and trace organic gas analyzers.
E N D
Tentative HIAPER Development Plan • Critical Infrastructure Dev. (10/1/04 – 4/30/05) • Pilot Proficiency (5/1/05 – 5/15/05) • Science Systems Flight Checks (5/15/05 – 6/15/05) • Progressive Science upload (6/15/05 – 8/15/05) • Progressive Science Research (8/15/05 – 12/15/05) • 1st Infrastructure Upgrade Package (1/1/06 – 3/1/06) • Available for Standard Research (3/1/06) • 2nd Infrastructure Upgrade Package (6/1/06 – 9/1/06) • 3rd Infrastructure Upgrade Package (6/1/07 – 7/10/07)
Projected HAIS Integration Schedule • Stratospheric Humidity - 9/1/2006 • Atmos. Radiation Pkg - 9/1/2006 • Small Ice Detector- 9/1/2006 • In-situ Ozone- 9/1/2006 • Whole Air Sampler- 9/1/2006 • Ozone Photometer- 9/1/2006 • Cascade Laser Spectrometer- 9/1/2006 • High Spectral Res. Lidar 1/1/2007 • GPS Profiler- 1/1/2007 • Cloud Radar- 9/1/2007 • Microwave Temperature Profiler- 9/1/2007 • Cloud Particle Imager- 9/1/2007 • Chemical Ion Mass Spec- 9/1/2007 • Aerosol Mass Spec- 9/1/2008 • Trace Organic Gas Analyzer- 9/1/2008
Tentative HIAPER Development PlanProjected Integration Schedule • Critical Infrastructure Period (10/1/04 – 6/15/05) • Basic science deliverables • Ground support equipment • Flight critical parts
Tentative HIAPER Development PlanProjected Integration Schedule • Progressive Science Period (6/15/05–12/15/05) • Community Exhaust • Dropsondes • Window blanks / remote sensing materials • Condensation Nuclei • Trailing Cone pressure calibration
Tentative HIAPER Development PlanProjected Integration Schedule • 1st Infrastructure Upgrade Package (1/1/06–3/1/06) • Optical View Ports / fused silica • Retractable View Port Covers • Radar Altimeter • Compressed gas cylinder mounts • Antennae
Tentative HIAPER Development PlanProjected Integration Schedule • 2nd Infrastructure Upgrade Package (6/1/06–9/1/06) • Radiometric Surface Temperatures • Digital Video • Wing Pylons / PMS Canister Mounts • Tail Deck Modifications & Wiring • Mission Scientist Station • Liquid Water & Icing Rate • Radiative Fluxes
Tentative HIAPER Development PlanProjected Integration Schedule • 3rd Infrastructure Upgrade Package (6/1/07 – 7/10/07) • All Weather Flux Pod* (11/15/06 – 12/15/06) • General Wing Pods / Large User Access