1 / 26

Chapter 5

Chapter 5. Much of Chap 5 and 6 varies depending on the contract type. Two major types are important so we’ll digress to Contracting 101 for a few charts. If interested in more details see Chapter 6 of text. Chapter 5. Chapter 5.

early
Télécharger la présentation

Chapter 5

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EMIS 7307 Chapter 5 • Much of Chap 5 and 6 varies depending on the contract type. • Two major types are important so we’ll digress to Contracting 101 for a few charts. • If interested in more details see Chapter 6 of text.

  2. EMIS 7307 Chapter 5

  3. EMIS 7307 Chapter 5 • The two types of contracts are Firm Fixed Price (FFP) and Cost Plus Fee (CPF). • FFP contracts are used when: • Producing product is low risk. • Making off the shelf purchases. • Potential willing bidders exist. • There is little, perhaps no, customer involvement during the execution of FFP contracts.

  4. EMIS 7307 Chapter 5 • CPF contracts are used when: • Producing system is perceived as high risk. • Potential bidders won’t bid on a FFP. • There is much customer involvement in the execution of CPF contracts. • Design reviews • Production reviews • Testing • ETC.

  5. EMIS 7307 Chapter 5 • Why is there so much customer involvement in the execution of CPF contracts? • Only have a target cost. If the costs exceed target customer still pays. • The system is so new and challenging it’s hard to know the requirements well, at the beginning. • This partially explains requirements creep.

  6. EMIS 7307 Range of Contract Types/Risk/Program Control (TYPES OF CONTRACTS) FFP CPFF FFP/EPA FPIF FPR T&MOR L/H CS CR CPIF CPAF (RISK) LOWHIGH BUYER HIGHLOW SELLER (PROJECT CONTROL) BUYER LESSMORE MORELESS SELLER Chapter 5 FFP = Firm Fixed Price CS = Cost Sharing FFP/EPA = Firm Fixed Price CR = Cost Reimbursement w/Economic Price Adjustments CPIF = Cost Plus Incentive Fee FPIF = Fixed Price Incentive Firm CPAF = Cost Plus Award Fee FPR = Fixed Price Redeterminable CPFF = Cost Plus Fixed Fee T&M = Time and Materials L/H = Labor Hour

  7. EMIS 7307 Chapter 5 • Design review general considerations: • Customer involvement not required in an FFP contract. • From a SE perspective no less important! • Event driven. • All the lead-up work complete else postpone! • Should be a phase culminating event. • Actual event should be anticlimactic.

  8. EMIS 7307 Chapter 5

  9. EMIS 7307 Chapter 5 • Figure 5.1 shows the author’s view of how design reviews, both formal and informal, fit into the process. • Next slide shows a government view. • Design reviews are gating functions. • Next phase doesn’t officially start until successful. • Design reviews fit into a bigger review picture as depicted in the second slide from here.

  10. EMIS 7307 Chapter 5

  11. EMIS 7307 Chapter 5

  12. EMIS 7307 Chapter 5 • Informal reviews are the many “mini” reviews (discussions) without the senior management or customer. • This is where the work is done to make sure the various design teams are ready for the formal reviews.

  13. EMIS 7307 Chapter 5 • Formal reviews at the system level cover items like those listed in Figure 5.4. • Typically every program has at least 3: • SRR • PDR • CDR • Look at Figure 5.6 for an example of tracking TPMs through the review process.

  14. EMIS 7307 Operational requirements Draft A spec Functional Analysis (block diagrams) Feasibility analysis (trade study results) Maintenance concept SEMP TEMP Draft TPMs Conceptual; design drawings Output is baseline functional design May consume as much as a week. Chapter 5 Conceptual Design Review also called SDR or SRR includes:

  15. EMIS 7307 Subsystems specs Draft Assembly specs “ilities reports” TPM analyses Engineering models/ prototypes Lab test results presented Supplier data Allocated baseline Test plans reviewed May consume the equivalent of a weeks time for each subsystem ~15% of the production drawings available Chapter 5 Preliminary Design Review (PDR) includes:

  16. EMIS 7307 Evaluates all Cis Evaluates product baseline Prelude to actual building and coding of system Product baseline Test plans reviewed May consume the equivalent of a weeks time for each assembly ~ 85% of the production drawings available Chapter 5 Critical Design Review (CDR) includes:

  17. EMIS 7307 Chapter 5 • For PDRs and CDRs the formal events will necessarily be capstone or summary events. • Action items are brought forward and results adjudicated. • From previous reviews. • From TIMs. • Sometimes reviews are given a pass to continue design, with a  review scheduled to finish the review some time in the future. •  reviews are for a few specific action items.

  18. EMIS 7307 Chapter 5 • Whenever we have a baseline what happens? • For some good (?) reason someone wants to change it! • Change control is a big issue from the beginning and gets bigger as time goes on. • More drawings that may need to change. • More drawings or products impacted if there is a change. • Remember, change control is required because of changes!

  19. EMIS 7307 Chapter 5 • Configuration management comprises: • Identification • Control • Status accounting • Audits

  20. EMIS 7307 Chapter 5 • Identification • Selection of CIs. • Determine types of documentation. • Documenting the functional and physical characteristics. • Establish interface management procedures. • Issuing numbers and identifiers.

  21. EMIS 7307 Chapter 5 • Control • Engineering change proposals. • Class 1- Form, fit, function changes. • Requires customer approval. • Class 2 - All other changes. • Configuration Control Board. • Request for deviation.

  22. EMIS 7307 Chapter 5

  23. EMIS 7307 Chapter 5

  24. EMIS 7307 Chapter 5 • Status accounting: • Lists of approved documents. • Status of proposed changes. • Implementation status. • Configuration of all units.

  25. EMIS 7307 Chapter 5 • Audits • Functional Configuration Audit (FCA) • Verifies actual performance of each CI meets specification. • Physical Configuration Audit (PCA) • Verifies as-built matches technical data package.

  26. EMIS 7307 Chapter 5 • Look at the 2 paragraphs near the bottom of page 245. • Another illustration that later is more costly.

More Related