1 / 11

Planning with Microsoft Project

Planning with Microsoft Project. Ivan Lloyd Corporate Project Solutions Ltd. Ivan_lloyd@cps.co.uk 07710 132013. Agenda. Do’s and Don’ts Key Issues MSP 2007 Stand Alone Highlights. Do’s & Don’ts. Do’s Use a template Display the Project Summary

edric
Télécharger la présentation

Planning with Microsoft Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Planning with Microsoft Project Ivan Lloyd Corporate Project Solutions Ltd Ivan_lloyd@cps.co.uk 07710 132013

  2. Agenda Do’s and Don’ts Key Issues MSP 2007 Stand Alone Highlights

  3. Do’s & Don’ts • Do’s • Use a template • Display the Project Summary • Set the working time & calendar to be equal if possible • Use one calendar • Use milestones for key events • Link all tasks • Baseline the project • Update the Project regularly • Assign resources to all tasks • Use target dates sparingly • Don’ts • Link summaries • Assign resource to summary tasks • Assign more than one resource

  4. The Global.mpt • Stores Personal Standards e.g. • Views • Fields • Tables • Calendars • Maintained using Organiser

  5. Calendars • Tools – Options – Calendar • Saved 1 per project and in the Global.mpt • Tools – Change Working Time • Defines Individual Working Calendars – available on the project on tasks & on resources • Start Time • End Time • Breaks • Non Working Days • Saved in the project (can be copied to global.mpt) • Can have many calendars • Ideally set both to be the same

  6. Task Types • Fixed Duration • Changing the Duration changes the Work • Changing the Units changes the Work • Changing the Work changes the Units • Fixed Units • Changing the Duration changes the Work • Changing the Units changes the Duration • Changing the Work changes the Duration • Fixed Work • Changing the Duration changes the Units • Changing the Units changes the Duration • Changing the Work changes the Duration

  7. Task Types • MS Default is Fixed Units, Effort Driven • Default setting is saved in the Global.mpt • Projects & Tasks can be different • Effort Driven • Only available for Fixed Work (Mandatory) & Fixed Units • Changes to units or work drive the assignment duration

  8. Progress Update • Set Status Date • Save an Interim Baseline • Update Task Progress • % Complete (Task related) • % Work Complete (Assignment related) • % Physical Complete • Reschedule uncompleted work • Re-plan

  9. 2007 Highlights Multi–level undo Change Highlights Task Drivers Cost Resources Visual Reporting

  10. What’s wrong?

  11. Next StepsAttend A Corporate Project Solutions Microsoft Project Training Course (CPS 300, 301 & 302)Book within the next 30days and receive a 15% discount Ivan_lloyd@cps.co.uk 07710 132013

More Related