RENAISSANCE LYON WP 2 Progress and Plan (Year 3- oct07 oct08). Christophe Ménézo A/Prof & INSA Lyon-CETHIL (Thermal Science Centre of Lyon) Christophe.menezo@insa-lyon.fr. WP 2.1 Electrical Network. Planned Activities:
E N D
RENAISSANCE LYON WP 2 Progress and Plan (Year 3- oct07 oct08) Christophe Ménézo A/Prof & INSA Lyon-CETHIL (Thermal Science Centre of Lyon) Christophe.menezo@insa-lyon.fr
WP 2.1 Electrical Network • Planned Activities: - Platform of measurements of the impact of the PV on the electrical distribution networks (at INSA of Lyon) - Measurements of the impact of PV systems installed in Lyon-Confluence Area on the distribution network
WP 2.1 Electrical Network • Measurement Platform at INSA Electricity quality evaluation produced by standard EN 50-160 inverter • Site : Electrical Engineering Dpt • Definition of platform objectives and design • Supplier (Tenesol) Done
WP 2.1 Electrical Network • Measurement series led on Lyon-Confluence Network • Project Submission to the National Research Agency (ANR) • Agreement between EDF R&D, INES RDI, Transénergie and INPGrenoble • Contact with INSA School of Electrical Engineering Master student subject Done
WP 2.1 Electrical Network • Measurement Platform at INSA Electricity quality evaluation produced by standard EN 50-160 inverter • Definition of the measurements protocol • Installation of the platform : 2 kWc • Installation of Practical Courses for Engineering Students of INSA • j Done Planed M24-M30
WP 2.1 Electrical Network • Measurement series led on Lyon-Confluence Network • Constructive data-gathering of the distribution network on the Lyon-Confluence area • Measurement Protocol definition with EDF R&D and INSA • Waiting for construction of the buildings and PhotoVoltaic systems
WP 2.2 Experience Feedback - Monitoring • Planned Activities: Multiscale Monitoring • Global Monitoring • Detailed Monitoring • Localised Monitoring ENERTECH
WP 2.2 Experience Feedback - Monitoring • Global Monitoring (promoters and dealers) - Counting and sub-counting heating room and sub-station and Solar Domestic Hot Water - Counting and under counting electricity in building • Detailed Monitoring (Enertech) -By housing - Followed Consumption: Cooking, lighting, washing machine - Followed thermal evolution • Localised Monitoring (INSA-CETHIL) -Some residences which have been numerically modeled ! Inhabitants !
WP 2.2 Experience Feedback - Monitoring Detailed Monitoring (Enertech) : expected results (such as in Restart Project) - Thermal Confort Human thermal gain Apartment Electricity Use Domestic Hot Water Domestic Hot Water distribution Common Electricity Use Cooking
WP 2.2 Experience Feedback - Monitoring Tests of sensors accuracy (INSA-CETHIL) Wireless sensors MINIBAT
WP 2.3 European Highlight • State of progress year 3: 6 first months • Monitoring strategy principles defined • but not fully planed at the moment (contributions of actors -Enertch-INSACETHIL-promotors-futur inhabitants, what as to be focused ventilation rate, energy performance of systems (envelop air tightness), apartment behavior (thermal comfort)) • Actually difficult to highlight Monitoring strategy Has to be fixed at a very short term
WP 2.3 European Highlight • Analysis of progress • Strong points : Zaragosa and Lyon not in phase • Experiences of Zaragosa not highlighted enough for Lyon • Networking opportunities should be much more used • (webcam exchange for regular exchange • for specific topics (focus), …)
WP 2.3 European Highlight • Plans for the next 6 months (end of year 3) • - Lyon strategy complete definition and planning of phases • Comparison with Zaragossa • - Common identification of what has to be highlight ? • Identification of strong/weak points on each side? • Definition of a monitoring strategy referential? • Key events … • INSA-CETHIL organize IBPSA France - Nov. 2008
ENERTECH ENERTECH WP leader contact WP 2 Olivier Sidler Sidler@club-internet.fr ENERTECH