An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. QSE Managers Working Group Report to WMS February 22, 2006 Report from February 15 Meeting

  2. Recommendation for Chair and Vice-chair • QSEMWG recommends Gary Miller of BTU as Chair • QSEMWG recommends Ron Wheeler of Dynegy as Vice-chair

  3. PRR 541 Recommendation • PRR 541 proposes to remove the 125% limit on regulation deployment in order to enhance frequency control. • Even with the current 125% limit, ERCOT Compliance doesn’t take this into account for SCE compliance. • PRR 541 will tend to exacerbate this issue, and QSEMWG recommends against passage.

  4. Resource Plan Performance Metrics: Score Averages Sept. ’04 to Jan. ‘06

  5. RRS Performance Monitoring Criteria • Suppose RRS is deployed @ 6:00 • RRS is fully recalled @ 6:15 • QSE performance is measured @ 6:10 • RRS deployed at 6:10 is used • QSE SCE must indicate at least 95% of RRS was deployed by not more 150%

  6. RRS Performance Monitoring Criteria • QSE A deployed 20 MW of RRS • SCE Lower Limit = (0.95 – 1) * 20 = -1 • SCE Upper Limit = (1 – 0.5) * 20 = 10 • To pass the criteria for this deployment: • QSE SCE @ 6:10 must be between -1 and 10 MW • QSE B deployed 50 MW of RRS • SCE Lower Limit = (0.95 – 1) * 50 = -2.5 • SCE Upper Limit = (1 – 0.5) * 50 = 25 • To pass the criteria for this deployment: • QSE SCE @ 6:10 must be between -2.5 and 25 MW

  7. RRS & NSRS Performance Monitoring Criteria • Working with PDCWG to draft a PRR to revise these criteria • Discussion is still ongoing

  8. DC Tie Automation Project • Automate Comparison of eTags to QSE DC Tie Schedules • Automate Operator offsets for DC Tie eTag/Schedule mismatches • Monitor/compare eTag Net Scheduled Interchange to DC Tie SCADA on EMS Display • Automate Inadvertent Energy Accounting

  9. Multiple BES Ramp Rate Feasibility

  10. Pre-processing outside of SPD Bid-1 Bid-2 Equiv. UBES RR=(100-20)/10=8 Equiv. UBES RR=(160-20)/10=14 Equiv. DBES RR=(140-0)/(10-2.5)=18.7 Equiv. DBES RR=(170-0)/(10-1.43)=19.8

  11. Claw-back provision in RMR contracts • WMS directed QSEMWG to investigate the significance of RMR capacity not offered in BES. • ERCOT will provide data on RMR units during bid stack depletion at the next QSEMWG meeting.