An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 10 Projects

  2. Learning Objectives • Explain what project management is and why it is important. • Identify the different ways projects can be structured. • Describe how projects are organized into major subprojects. • Understand what a project milestone is. • Determine the “critical path” for a project. • Demonstrate how to “crash,” or reduce the length, of a project.

  3. What is Project Management? • Project: • A series of related jobs usually directed toward some major output and requiring a significant period of time to perform • Usually infrequent • Exact duration difficult to estimate • Project management: • The management activities of planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project • Control may be difficult • Makeup of the project team • Expert among experts LO 1

  4. Types of Development Projects LO 2

  5. Structuring Projects • Pure project • Functional project • Matrix project LO 2

  6. Pure Project • In Pure Project Self-contained team works full-time on the project • Advantages • The project manager has full authority • Team members report to one boss • Shortened communication lines • Team pride, motivation, and commitment are high LO 2

  7. Pure Project • Disadvantages • Duplication of resources • Equipment and people not shared across projects • Organizational goals and policies are ignored • Team members detached from headquarters • Lack of technology transfer • Due to weakened functional division • Team members have no functional area "home“ • Project termination often delayed as members worry about life after the project LO 2

  8. Functional Project A functional project is housed within a functional division. Example: Project “B” is in the functional area of Research and Development LO 2

  9. Functional Project • Advantages • A team member can work on several projects • Technical expertise maintained in functional area • Functional area is “home” after project completed • Critical mass of specialized knowledge • Disadvantages • Aspects of the project that are not directly related to the functional area get short-changed • Motivation of team members is often weak • Needs of the client are secondary and are responded to slowly LO 2

  10. Matrix Project LO 2

  11. Matrix Project • Advantages • Better communications between functional areas • Project manager held responsible for success • Duplication of resources is minimized • Functional “home” for team members • Policies of the parent organization are followed • Disadvantages • Too many bosses • Functional manager often listened to first because of direct influence on promotion and raises • Depends on project manager’s negotiating skills • Potential for sub-optimization • PM’s could hold resources for own projects • Other projects could be harmed LO 2

  12. Phases of Project Management • Planning • Work breakdown structure • Feasibility study • Precedence determination • Scheduling • Construct the chart and apply times • Identify priorities • Execution and control • Review and modify the project

  13. Work Breakdown Structure • Statement of work (SOW): a written description of the objectives to be achieved • Task: a further subdivision of a project • Usually shorter than several months • Performed by one group or organization • Work package: a group of activities combined to be assignable to a single organizational unit • Project milestones: specific events on the project LO 3

  14. Work Breakdown Structure • Work breakdown structure (WBS): defines the hierarchy of project tasks, subtasks, and work packages • Defines hierarchy of project tasks, subtasks and work packages • Allows the elements to be worked on independently • Make team manageable in size • Give authority to carry out the project • Monitor and measure the project • Provide the required resources • Activities: pieces of work that consume time • Defined within the context of the WBS LO 4

  15. An Example of a Work Breakdown Structure Quality is Job 1 ISO 9001 MPG Data Collection Taurus, Sable LO 3

  16. Work Breakdown Structure, Large Optical Scanner Design LO 3

  17. Project Control Charts • Charts are useful because their visual presentation is easily understood • Software is available to create the charts • Gantt chart: a bar chart showing both the amount of time involved and the sequence in which activities can be performed LO 3

  18. Sample of Graphic Project Reports LO 3

  19. Earned Value Management (EVM) • A technique for measuring project progress in an objective manner • Has the ability to combine measurements of scope, schedule, and cost in a project • Provides a method for evaluating the relative success of a project at a point in time LO 3

  20. Essential Features of any EVM Implementation • A project plan that identifies the activities to be accomplished • A valuation of each activity work • Predefined earning or costing rules to quantify the accomplishment of work LO 3

  21. Earned Value Management Charts LO 3

  22. Project Tracking Without EVM • Chart A shows the cumulative cost budget for the project as a function of time • Blue line, labeled BCWS • Also shows the cumulative actual cost of the project • Red line • Appears project was over budget through week 4 and then under budget • What is missing is any understanding of how much work has been accomplished LO 3

  23. Project Tracking With EVM • Chart B shows the BCWS curve along with the BCWP curve from chart A • Technical performance started more rapidly than planned but then slowed significantly and feel behind at week 7 • Chart illustrates the schedule performance aspect of EVM LO 3

  24. Project Tracking With EVM • Chart C shows the same BCWP curve with actual cost data • Project is actually under budget, relative to the amount of work accomplished • Chart D shows all three curves together • Typical for EVM line charts LO 3

  25. Example: Earned Value Management LO 3

  26. Example: Budgeted Cost of Work Scheduled (BCWS) • 100% of $18K = $18K • 100% of $10K = $10K • 80% of $20K = $16K • 15% of $40K = $6K BCWS = $18K+$10K+$16K+$6K = $50K LO 3

  27. Example: Budgeted Cost of Work Performed (BCWP) • 100% of $18K = $18K • 80% of $10K = $8K • 70% of $20K = $14K • 0% of $40K = $0 BCWP = $18K+$8K+$14K+$0 = $40K LO 3

  28. Example: Performance Measures LO 3

  29. Network-Planning Models • A project is made up of a sequence of activities that form a network representing a project • The path taking longest time through this network of activities is called the “critical path” • The critical path provides a wide range of scheduling information useful in managing a project • Critical path method (CPM) helps to identify the critical path(s) in the project networks LO 3

  30. Prerequisites for Critical Path Methodology • A project must have: • well-defined jobs or tasks whose completion marks the end of the project; • independent jobs or tasks; • and tasks that follow a given sequence.

  31. Types of Critical Path Methods • CPM with a Single Time Estimate • Used when activity times are known with certainty • Used to determine timing estimates for the project, each activity in the project, and slack time for activities • CPM with Three Activity Time Estimates • Used when activity times are uncertain • Used to obtain the same information as the Single Time Estimate model and probability information • Time-Cost Models • Used when cost trade-off information is a major consideration in planning • Used to determine the least cost in reducing total project time

  32. Critical Path Method (CPM) • Identify each activity to be done and estimate how long it will take • Determine the required sequence and construct a network diagram • Determine the critical path • Obtain all project and activity timing information • Determine the early start/finish and late start/finish schedule LO 5

  33. Example 1: Critical Path Method (Single Time Estimate) LO 5

  34. Example 1: Activity Sequencing and Network Construction LO 5

  35. Determining the Critical Path & Slack • A path is a sequence of connected activities running from start to end node in a network • The critical path is the path with the longest duration in the network • It is also the minimum time, under normal conditions, to complete the project • Delaying activities on the critical path will delay completion time for the project • A slack is amount of scheduling flexibility • Critical activities have no slacks

  36. Example 1: Finished Schedule Forward Pass Backward Pass SLACK=LS-ES=LF-EF Slack=(36-33)=(31-28)=3 A PATH IS CRITICAL IF: ES=LS, EF=LF, and EF-ES=LF-LS=D LO 5

  37. Critical Path Method:Three Activity Time Estimates • If a single time estimate is not reliable, then use three time estimates • Task times assumed variable (probabilistic) • Minimum (optimistic) • Maximum (pessimistic) • Most likely (normally) • Allows us to obtain a probability estimate for completion time for the project LO 5

  38. Finding Activity Time and Variance LO 5

  39. Example 2: Activity Expected Times and Variances Variance of Project = Sum of Variance of Activities on CP LO 5

  40. Example: Network with Three Time Estimates LO 5

  41. Probability Estimates p(t < D) t TE = 38 D=35 From Appendix G, page 765 There is about a 19.78% probability that this project will be completed in 35 weeks or less.

  42. p(t < D) t TE = 38 Probability Estimates 0.95994 D=44 There is about a 4% probability that this project will not be completed in 44 weeks.

  43. Time-Cost Models and Project Crashing • Basic assumption: Relationship between activity completion time and project cost • Time cost models: Determine the optimum point in time-cost tradeoffs • Activity direct costs • Project indirect costs • Activity completion times LO 6

  44. Time-Cost Models and Project Crashing Cost $ CC 100+C Rate of Change = 100+B CC-NC 100+A 100 NC Time 5 10 20 30 CT NT NT-CT

  45. Procedure for Project Crashing • Prepare a CPM-type network diagram • Normal and crash times for each • Normal and crash costs for each • Determine the cost per unit of time to expedite each activity • Incremental cost = (CC-NC)/(NT-CT) • Compute the critical path • Shorten the critical path at the least cost • Plot project direct, indirect, and total-cost curves and find the minimum-cost schedule LO 6

  46. Time-Cost Model: Example For the project with the following times, find the cost of reducing its duration to its lowest possible time. If the project is reduced by just 2 days, how much would it cost? CRASH NORMAL Activity Time Cost Time Cost IN CL=NT-CT A 2 6 1 10 B 5 9 2 18 C 4 6 3 8 D 3 5 1 9 4 1 3 3 2 1 2 2

  47. NORMAL CRASHED 1 2 ES= EF= ES= EF= B B ,2 ,5 10 5 ES= EF= ES= EF= ES= EF= ES= EF= LS= LF= LS= LF= A A D D ,1 ,1 ,2 ,3 LS= LF= LS= LF= LS= LF= LS= LF= ES= EF= ES= EF= C C ,4 $26 ,3 $45 LS= LF= LS= LF= ES= EF= ES= EF= 3 4 B B ,2 ,5 8 7 ES= EF= ES= EF= ES= EF= ES= EF= LS= LF= LS= LF= A A D ,1 D ,2 ,2 ,1 LS= LF= LS= LF= LS= LF= LS= LF= ES= EF= ES= EF= C C $30 ,4 ,4 $39 LS= LF= LS= LF=

  48. 1 2 ES= EF= ES= EF= B B ,4 ,4 7 6 ES= EF= ES= EF= ES= EF= ES= EF= LS= LF= LS= LF= A A D D ,2 ,1 ,1 ,1 LS= LF= LS= LF= LS= LF= LS= LF= ES= EF= ES= EF= $33 C C ,4 ,4 $37 LS= LF= LS= LF= ES= EF= ES= EF= 3 4 B B ,3 5 ES= EF= ES= EF= ES= EF= ES= EF= LS= LF= LS= LF= A A D D ,1 ,1 LS= LF= LS= LF= LS= LF= LS= LF= ES= EF= ES= EF= C C ,3 $42 LS= LF= LS= LF=

  49. CPM Assumptions/ Limitations • Project activities can be identified as entities (There is a clear beginning and ending point for each activity.) • But this is seldom true • Project activity sequence relationships can be specified and networked • Sometime we do not know all project activities ahead of time

  50. CPM Assumptions/ Limitations • Project control should focus on the critical path • But there are near-critical activities • The activity times follow the beta distribution, with the variance of the project assumed to equal the sum of the variances along the critical path • But activities are infrequent. Can we assume normality? • Are we really sure that it is beta distributed?