1 / 9

Planned activities on collimator for LS1

Planned activities on collimator for LS1. O . Aberle – 25/03/13 With input from P. Bestmann, S. De Man and F. Loprete. Main activities during the LS1. TDI.4R8 and TDI.4L2 Collimator exchange Collimator standard maintenance TIM / Robot intervention / observations Alignment

ernie
Télécharger la présentation

Planned activities on collimator for LS1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Planned activities on collimator for LS1 O. Aberle – 25/03/13 With input from P. Bestmann, S. De Man and F. Loprete

  2. Main activitiesduringthe LS1 • TDI.4R8 and TDI.4L2 • Collimatorexchange • Collimatorstandardmaintenance • TIM / Robot intervention/observations • Alignment • Outlook O. Aberle – CWC

  3. TDI‘sduring LS1 until LS2 • TDI.4L2 (TDI 001 will be replaced by reconditioned spare(TDI 003) (Oct? – Nov?) • TDI.4L2 (TDI 001) will upgraded with the new beam screen and additional temperature sensors, for installation in Pt. 8 • Installation in slot TDI.4R8 • Old TDI.4R8 (TDI 002) to be reconditioned, prepared as spare Pt. 2 • Produce a new TDI 004 as spare for Pt. 8 • After LS 1 four TDI’s with new beam screens, two installed, two spares • New design for LIU for LS2 O. Aberle – CWC

  4. Collimatorexchange • New production of 16 + 4 TCTP • New production of 2 + 1 TCSP • New production of 2 + 1 TCAPD • Preparation of 2 spare TCLP • Preparation of 1 spare TCP • Layout modification in Pt. 8, removal of 2 TCTVB, shifting TCLIA • Pt. 1: Replacement of 4 TCT + by 4TCTP + installation of 2 TCLP • Pt. 2: Replacement of 2 TCT + 2 TCLP by 4 TCTP • Pt. 3: Installation of 2 new TCAPD • Pt. 5: Replacement of 4 TCT + by 4TCTP + installation of 2 TCLP • Pt. 6: Replacement of 2 TCS by 2 TCSP • Pt. 7: Remove first two TCP per beam during ventilation door installation (to prevent damage) and exchange the skewed TCP of IR7L • Pt. 8: Replacement of 2 TCT + 2 TCTVB by 4 TCTP O. Aberle – CWC

  5. Collimatorstandardmaintenance • Check each collimator mechanics and electronics. • Cycle from out to in, to anti-collision and back to out. • Check 5th axis for clearance • Check water cooling flow • Check temperature sensors • Check switches, LVDT’s, resolvers, motors and drivers • Map sound profile for each collimator • Check rails • Check roller screws O. Aberle – CWC

  6. Collimatorrollerscrewreplacement (2011-12) Dustanddebris in the end capandthehousing Some dry screwsregreased Uptodate 3 rollersscrewshavebeenexchanged. -No linear bearing -2 LVDT‘s -1 motor -2 switches O. Aberle – CWC

  7. TIM andRobot intervention • Sound inspection of the collimators done with the TIM in S34 (23/24 April 2012). • Visual and acoustic inspections with camera can be useful in the future (TIM automatically, Telemax robot more flexible). • Vacuum disconnection testing with the Telemax robot on-going. • Use of robot for visual inspections/leak tests (He spray). • Profit from the long shutdown to verify the integration and do some hardware tests to confirm the procedures. O. Aberle – CWC

  8. Alignment • Survey is working in the whole machine. • During smoothing, magnets will be aligned and collimators checked (and adjusted if needed). • IR 3 and IR 7 are equipped with additional targets for remote verification with the stretched wire. • New collimators (TCTP, TCSP and TCAPD) will be aligned. • The TCP’s removed during the installation of the ventilation doors + the skewed TCP in IR7L to be checked (high radiation levels, how much deviation can be tolerated?). O. Aberle – CWC

  9. Outlook • Improve the sound and image quality for the TIM, very powerful tool for the future. • Investigate on the capabilities of the Telemax or similarrobots for inspections and interventions. • Reference sound recording of all collimators. • Improve the accessibility to the screw (cap) (Phase 2!) • A regular check during long breaks and shut-downs with re-lubrication of the screw. • Automatic motion cycles during LS1 to be planned. • Check every slot for 5th axis motion limitations. O. Aberle – CWC

More Related