An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UNDP - GEF Project: UKR/01/G31/A/1G/99 Climate Change Mitigation in Ukraine through Energy Efficiency in Municipal District Heating Pilot Project in Rivne

  2. Main Items • Major Barriers and Lessons learnt • Best Practices • Challenge for future

  3. ACCESS TO FINANCE Strategic Priority #2(UNDP/GEF Business Plan): Goal: Creation of the Municipal Energy Service Company (ESCO)

  4. UNDP - GEF Project: UKR/01/G31/A/1G/99 Demonstration Project: • Energy Efficiency and Economical effect • Ecological (Environmental) Effect • Social effect

  5. MAJOR BARRIERS • Inappropriate Institutional Approach • Lack of Community Participation • Absence of Local Capacity

  6. INSTITUTIONAL APPROACH • Project Initial Strategy – NEX SCEC (State Committee for Energy Conservation) • Currently NEX – Local (Oblast) Administration • Changes Introduced

  7. INSTITUTIONAL CHANGES THE FOLLOWING CHANGES HAVE TAKEN PLACE: • The Project management was moved to the local level; • Oblast Administration was nominated a national executing agency andthe State Committee dismissed from this responsibility. • As Result the Project Support Office in Kiev was closedand Project Implementation Office in Rivne became to be the only Project office.

  8. COMMUNITY MOBILIZATION • Lack of appropriate Methodologies in Ukraine • No prior experience and field work in practice

  9. UNDP - GEF Project: UKR/01/G31/A/1G/99 Lessons learnt: • Selecting partners with capacity to understand and work with international assistance • Success when local partners own and manage

  10. Best Practices • Mayor’s personal involvement and support • Governor’s office support • Sound and fruitful cooperation between municipality and business (Komunenergia) • Community mobilization and involvement

  11. During 2004 • Capacity Building of the “ESCO-Rivne”: • ESCO Support Activities, • Strategic Business Plan for ESCO-Rivne • Energy Efficiency Plan for Rivne city launched • Community Mobilization; • Experience Dissemination and Replication country wide; • Preparation to the Stage 2.