1 / 35

Outline

Outline. Control structure design (plantwide control) A procedure for control structure design I Top Down Step 1: Degrees of freedom Step 2: Operational objectives (optimal operation) Step 3: What to control ? (self-optimzing control) Step 4: Where set production rate? II Bottom Up

gali
Télécharger la présentation

Outline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Outline • Control structure design (plantwide control) • A procedure for control structure design I Top Down • Step 1: Degrees of freedom • Step 2: Operational objectives (optimal operation) • Step 3: What to control ? (self-optimzing control) • Step 4: Where set production rate? II Bottom Up • Step 5: Regulatory control: What more to control ? • Step 6: Supervisory control • Step 7: Real-time optimization • Case studies

  2. Step 4. Where set production rate? • Where locale the TPM (throughput manipulator)? • Very important! • Determines structure of remaining inventory (level) control system • Set production rate at (dynamic) bottleneck • Link between Top-down and Bottom-up parts

  3. TPM (Throughput manipulator) • TPM (Throughput manipulator) = ”Unused” degree of freedom that affects the throughput. • Definition (Aske and Skogestad, 2009). A TPM is a degree of freedom that affects the network flow and which is not directly or indirectly determined by the control of the individual units, including their inventory control. • Usually set by the operator (manual control), often the main feedrate • The TPM is usually a flow (or closely related to a flow) but not always. • One exception is for a reactor where the reactor temperature can be a TPM, because this changes the reactor conversion, which changes the production rate and thus the throughput • Usually, only one TPM for a plant, but there can be more if there are • parallel units or splits into alternative processing routes • multiple feeds that do not need to be set in a fixed ratio • The feeds usually need to be set in a fixed ratio. For example, for the reaction A+B-> product we need to have the ratio FA/FB close to 1 to have good operation with small loss of reactants, so there is only one TPM even if there are two feeds, FA and FB. • If we consider only part of the plant then the TPM may be outside our control. The throughput is then a disturbance which is typically a given feedrate (if our plant is a postprocessing plant) or a given product rate (preprocessing or utility plant) • If the TPM becomes unavailable because of saturation as we enter a new region, then a potential new TPM is a variable that is no linger self-optimizing.

  4. Reactor-recycle process:Given feedrate with production rate set at inlet TPM

  5. Consistency of inventory control • Consistency (required property): An inventory control system is said to be consistentif the steady-state mass balances (total, components and phases) are satisfied for any part of the process, including the individual units and the overall plant. • Local*-consistency (desired property): A consistent inventory control system is said to be local-consistent if for any part/unit thelocalinventory control loops by themselves are sufficient to achieve steady-state mass balance consistency for that unit (without relying on other loops being closed). * Previously called self-consistency

  6. Local-consistency rule(also called self-consistency) Rule 1. Local-consistency requires that 1. The total inventory (mass) of any part of the process must be locally regulated by its in- or outflows, which implies that at least one flow in or out of any part of the process must depend on the inventory inside that part of the process. 2. For systems with several components, the inventory of each component of any part of the process must be locally regulated by its in- or outflows or by chemical reaction. 3. For systems with several phases, the inventory of each phase of any part of the process must be locally regulated by its in- or outflows or by phase transition. Proof: Mass balances Note: Without the local requirement one gets the more general consistency rule

  7. CONSISTENT?

  8. TPM TPM

  9. Production rate set at inlet :Inventory control in direction of flow* TPM * Required to get “local-consistent” inventory control

  10. Production rate set at outlet:Inventory control opposite flow TPM

  11. Production rate set inside process TPM

  12. Summary

  13. QUIZ. Consistent? Local-consistent? Note: Local-consistent is more strict as it implies consistent

  14. Closed system: Must leave one inventory uncontrolled

  15. Where set the production rate? • Very important decision that determines the structure of the rest of the control system! • May also have important economic implications

  16. Often optimal: Set production rate at bottleneck! • "A bottleneck is a unit where we reach a constraints which makes further increase in throughput infeasible" • If feed is cheap and available: Optimal to set production rate at bottleneck • If the flow for some time is not at its maximum through the bottleneck, then this loss can never be recovered.

  17. RECALL: Back-off for CV-constraints feedrate Loss Jopt backoff c = bottleneck constraint Copt Cs = cmin + backoff Backoff = meas.error (bias) + dynamic control error Dynamic control error can = variance Rule: “Squeeze and shift” Reduce variance (“Squeeze”) and reduce backoff (“shift”)

  18. Alt.1. Feedrate controls bottleneck flow (“long loop”…): Fmax FC Fmax Alt. 3: Reconfigure all upstream inventory loops: Fmax Single-loop alternatives for bottleneck control Bottleneck. Want max flow here Traditional: Manual control of feed rate TPM TPM Alt. 2: Feedrate controls lost task (another “long loop”…): TPM TPM

  19. Alt. 1D: Feedrate controls bottleneck flow + “feedforward”: Fmax FC Alt. 2D: Feedrate controls lost task + “feedforward”: Fmax Possible improvements TPM TPM Alt. 4: MPC

  20. Reactor-recycle process: Want to maximize feedrate: reach bottleneck in column Bottleneck: max. vapor rate in column TPM

  21. Reactor-recycle process with max. feedrateAlt.1: Feedrate controls bottleneck flow Bottleneck: max. vapor rate in column TPM Vs FC Vmax V Vmax-Vs=Back-off = Loss Get “long loop”: Need back-off in V

  22. Reactor-recycle process with max. feedrate:Alt. 2Optimal: Set production rate at bottleneck (MAX) Feedrate used for lost task (xb) Bottleneck: max. vapor rate in column MAX TPM Get “long loop”: May need back-off in xB instead…

  23. MAX Reactor-recycle process with max. feedrate:Alt. 3:Optimal: Set production rate at bottleneck (MAX)Reconfigure upstream loops TPM OK, but reconfiguration undesirable…

  24. Reactor-recycle process:Alt.3: reconfigure (permanently) TPM F0s For cases with given feedrate: Get “long loop” but no associated loss

  25. Reactor-recycle process with max. feedrateAlt.1D: Alt. 1 “Long loop” + “feedforward” Bottleneck: max. vapor rate in column TPM F/F0 Vs FC “Feedforward”: Send feed change to ALL flows upstream bottleneck Less back-off in V because F closer to V

  26. Reactor-recycle process with max. feedrateAlt.2D: Alt. 2 “Long loop” + “feedforward” F/F0 MAX TPM “Feedforward”: Send flow change to ALL flows upstream bottleneck Less back-off in xB because F closer to xB

  27. Alt.4: Multivariable control (MPC) • Can reduce loss • BUT: Is generally placed on top of the regulatory control system (including level loops), so it still important where the production rate is set!

  28. Conclusion production rate manipulator • Think carefully about where to place it! • Difficult to undo later • One approach: Put MPC gtop that coordinates flows through plant • By manipulating feed rate and other ”unused” degrees of freedom: • E.M.B. Aske, S. Strand and S. Skogestad, • ``Coordinator MPC for maximizing plant throughput'', • Computers and Chemical Engineering, 32, 195-204 (2008).

  29. QUIZ. Distillation. OK? LV-configuration TPM

  30. DB-configuration OK???

  31. QUIZ • Cases 7–13, 15-23 • Will it work? Where is throughput set (TPM)?

  32. LOCATE TPM? • For step 4, locate TPM, the procedure is: • As the default choice place the TPM at the feed • Consider moving if there is an important active constraint that could otherwise not be well controlled. That is, if the feedrate must be used for some other task in order to get a local-consistent system with tight control of the constraint. • To avoid the need to move (reassign) the TPM, avoid variables that may saturate. • Exception to (c): The last constraint to become active when we reach optimum or maximum throughput* is a good candidate TPM, because the bottleneck situation is generally where the backoff losses are largest. Also, this TPM will only saturate when it no longer can be increased, so no change in TPM-variable is ever needed. *At optimum/maximum throughput, the throughput can no longer be set (because it is used a degree of freedom for optimal operation)

More Related