An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Analisa Network

  2. Ada 2 Metode Yang umudigunakan • CPM (Critical Path Method) • PERT (Program Evaluation and Review Technique)

  3. Diagram Jaringan Kerja • PerancanganProyek • Gambarkegiatanproyek • Simbol – simbol yang digunakan : 1. AnakPanah Menyatakankegiatan Gambar : 2. AnakPanahTerputus – putus Menyatakankegiatansemuatau Dummy Gambar :

  4. 3. Anak Panah dengan garis sejajar atau tebal Gambar : 4. Peristiwa Menyatakan Peristiwa atau suatu kejadian Gambar : MenyatakanJalurkritis, jalurkritisjalur terpanjangdarijaringankerja

  5. Metode CPM (Critical Path Method) • Earliest Start Time (ES) : waktutercepatuntukbisamemulaisuatukegiatandenganwaktu normal, tanpamengganggukegiatan lain • Latest Start Time (LS) : waktu paling lambatuntukbisamemulaikegiatandenganwaktu normal, tanpamenggangukegiatan-kegiatanlainnya • Earliest Finish Time (EF) : waktu paling cepatuntukmenyelesaikansuatupekerjaandalamwaktu normal, tanpamengganggukegiatan lain • Latest Finish Time (LF) : waktu paling lambatuntukmenyelesaikansuatukegiatandalamwaktu normal, tanpamengganggukegiatan lain

  6. Contoh Soal

  7. Network C F 3 4 5 6 5 A H 2 8 D 7 1 4 B 8 12 6 7 2 E G

  8. Menghitung ESi

  9. Menghitung LSi

  10. Memeriksa kegiatan Kritis • Kegiatan A ES1 = LS1  0 = 0 ES3 = LS3  4 ≠ 7 ES1 + t13= ES3  0 + 2 = 4  2 ≠ 4 • Kegiatan B ES1 = LS1  0 = 0 ES2 = LS2  4 = 4 ES1 + t12 = ES2  0 + 4 = 4  4= 4 • Kegiatan D ES2 = LS2  4 = 4 ES4 = LS4  12 = 12 ES2 + t24 = ES4  4 + 8 = 12  12= 12

  11. Kegiatan E ES2 = LS2  4 = 4 ES6 = LS6  18 = 18 ES2 + t26 = ES6  4 + 12 = 18  16 ≠ 18 • Kegiatan F ES4 = LS4  12 = 12 ES5 = LS5  18 = 18 ES4 + t45 = ES5  12 + 6 = 18  18 = 18 • Kegiatan H ES5 = LS5  18 = 18 ES7 = LS7  26 = 26 ES5 + t57 = ES7  18 + 7 = 26  25 ≠ 26 • Kegiatan G ES6 = LS6  18 = 18 ES7 = LS7  26 = 26 ES6 + t67 = ES7  18 + 8 = 26  26 = 26

  12. Kegiatan Kritis : B, D, F, Dummy 2, G • Jalur Kritisnya : 1 – 2 – 4 – 5 – 6 – 7 • Waktu Kritisnya : 4 + 8 + 6 + 0 + 8 = 26 • Waktu penyelesaian persoalan diatas minimal 26 minggu C F 4 12 18 3 4 5 12 18 7 6 5 A H 2 8 0 D 7 Dummy 2 Dummy 1 1 0 4 B 8 4 12 26 18 6 7 2 E G 18 26 4