1 / 4

Spectrometer Solenoids MICO 230 Steve Virostek LBNL August 7, 2013

Spectrometer Solenoids MICO 230 Steve Virostek LBNL August 7, 2013. The magnet was cooled down to LHe temperature two weeks ago. Iron shield with 60 cm hole has been mounted.

guang
Télécharger la présentation

Spectrometer Solenoids MICO 230 Steve Virostek LBNL August 7, 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Spectrometer SolenoidsMICO 230Steve VirostekLBNLAugust 7, 2013

  2. The magnet was cooled down to LHe temperature two weeks ago. • Iron shield with 60 cm hole has been mounted. • Low current testing (up to 50 A) revealed resistive behavior in the E2 coil 500 A HTS lead – worse than previous failed HTS lead. • All other HTS and LTS leads appeared normal; PS’s were working well. • With shield cold, system was not quite condensing He fast enough to pull cold mass pressure downward. • Current thinking is that the issue is related to cryocooler performance. • No indications of excessive heat leak to cold mass at this point. • System is now being warmed up in order to replace bad HTS lead and to swap out at least three cryocoolers. • We expect to be ready for cool down again one week from today and possibly ready to commence training on August 19th. Status of SS1

  3. Status of SS2 • All training and magnetic mapping are complete. • Magnet is warm and being prepared to ship (delayed due to SS1 work). • Two-stage cryocoolers have been removed. • Iron shield has been removed, brackets are being removed. • Rigging company representative has visited Wang to discuss loading of magnet onto truck for delivery to airport. • LBNL shipping company (Aeronet) representatives have visited Wang to discuss various shipping options – quote forthcoming. • Custom shipping pallet with shock isolators are now on hand. • Crates for additional hardware are all on hand (6 crates total for cooler heads, compressors, hoses, iron shield, brackets, misc hdw.). • Necessary paperwork is being assembled.

  4. Milestone Update Upstream Spectrometer Solenoid (SS2) • Ready for shipping: revised to 21-Aug-13 • Delayed due to prep and repair work on SS1 • SS#2 at RAL: revised to 04-Sep-13 Downstream Spectrometer Solenoid (SS1) • Acceptance tests complete: revised to 06-Sep-13 • Delayed due to bad HTS lead requiring warm up and repair • Field mapping complete: revised to 20-Sep-13 • Ready for shipping: revised to 04-Oct-13 • SS#2 at RAL: revised to 18-Oct-13

More Related