MS Project

MS Project. Duration Work Resource Resource Units Effort-Driven. Fixed Duration Fixed Units Fixed Work Over-allocation Leveling. Terms. Duration & Work. Duration - The total span of working time or elapsed time required to complete a task.

gwylan
Télécharger la présentation

MS Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MS Project

  2. Duration Work Resource Resource Units Effort-Driven Fixed Duration Fixed Units Fixed Work Over-allocation Leveling Terms

  3. Duration & Work • Duration - The total span of working time or elapsed time required to complete a task. • Work - The total effort required to complete a task.

  4. Resources • Resources are the people, equipment and supplies used to complete tasks in a project. • Resources that are assigned to tasks but do not create work are known as material resources. • Resource Units indicate how much of a resource's available time, according to the resource calendar, is being used to work on a particular task. In a project schedule, resource effort is expressed as assignment units or sometimes just as units.

  5. Scheduling Formula Duration = Work ÷ Resource Units

  6. Fixed Units • As the task's assigned units remain constant, an increase / decrease in assigned work will result in a corresponding increase / decrease in task duration. • Fixed Units is the default task type for new tasks.

  7. Fixed Work • If assigned work should remain constant, then as a task's duration goes up assigned units will go down (and vice versa). • If assigned units are greater than max units, a resource over-allocation will arise. • Duration = Work ÷ Resource Units • or Duration = 1 ÷ Resource Units

  8. Fixed Duration • For a constant task duration, as assigned work is increased so will assigned units. • Decrease the units and the work will correspondingly reduce. • Duration = Work ÷ Resource Units • If assigned units are greater than max units, a resource over-allocation will arise.

  9. Effort-Driven • Only comes into play after the initial resource assignments have been made • Work stays constant • When resources (manpower) are assigned or removed from a task, Microsoft Project will extend or shorten the duration of the task to accommodate change in resources • This is the default option for new tasks

  10. Over-allocation • Situation when more hours of a resource are allocated than are available • Identifying Over-allocated Resources • Special leveling indicator • Resource Usage View – over-allocated resources are red • Over-allocation can be resolved by leveling project

  11. Leveling • Resolving resource conflicts or over-allocations by delaying or splitting certain tasks. • During leveling, assignments are rescheduled according to the resource availability profiles, assigned units, and resource calendars, as well as the task's duration and constraints. • It is instigated either automatically or (more commonly) by the command level now. • Tools | Level Resources . . . (hour by hour)

  12. Questions?