1 / 58

Gloucester High School Master Plan: School Board Update

Get the latest update on Gloucester High School's master plan, including assessments of the facility's civil, architectural, roofing, structural, mechanical, electrical, and plumbing systems.

hardrickm
Télécharger la présentation

Gloucester High School Master Plan: School Board Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gloucester High School Master Plan School Board Update January 24, 2018

  2. Facility Assessment • Civil • Architectural • Roofing • Structural • Mechanical • Electrical • Plumbing

  3. Civil • Parking Lots • Significant cracking • Patches throughout • Drainage flumes eroded and undermined • General wear and tear throughout • Parking lots: Fair Condition • Athletic Facilities • Tennis Courts: Fair condition • Softball: Good condition • Baseball: Good condition • Stadium & Track: Good condition • Practice Fields: Good condition • Consider • ADA seating • Bathroom facilities • Concessions • Press Box

  4. ADA • Non-compliant casework • Non-compliant door hardware • Non-compliant drinking fountains • Non-compliant toilet rooms. • Insufficient clearance • Missing grab bars • Non-compliant fixtures • Non-compliant ramp. • Vertical change in elevation exceeds what is allowable for single ramp. • Missing handrails • Doors opening on to ramp.

  5. Architectural • Ceilings • 2x2 lay-in ceiling tiles • Poor to Good Condition • Would need to be removed if above ceiling work is performed (Sprinkler, HVAC) • Casework • Poor to Fair Condition • Many instances of Non ADA accessible design • Floors • Terrazzo: Good condition • VCT: Poor to Good condition

  6. Architectural • Lockers • Corridor Lockers: Good Condition • Athletic Lockers: Poor Condition • Doors • Poor to Fair Condition • New doors would need to be Fire Rated with closers to comply with Code requirements (unless sprinkler system is installed) • Interior Finishes • Types Vary; Poor to Good Condition

  7. Architectural • Windows • Hollow metal frames • Evidence of rusting on some frames • Fair to Good condition • Visual Display Surfaces • Chalkboards • Whiteboards • Smartboards

  8. Roofing • Poor Condition • Requires restoration within next 2-3 years • Fair Condition • Requires restoration within next 12-15 years • Good condition • Requires restoration within next 15 years • Some repair work required now

  9. Structural • Structural System • Good Condition • Minor cracks were observed but do not present a structural concern. • Lateral bracing will be required in order to meet current Codes if interior partitions are modified

  10. Mechanical | AHUs & RTUs Roof Top Units Life Expectancy Condition Age Quantity Poor Fair Good 14 RTUs 6 RTUs 2 RTUs 24 years old 12 years old 8 years old 15 years 15 years 15 years Air Handling Units AHU 1 AHU 2 AHU 3 AHU 4 AHU 5 AHU 6 44 years old 44 years old 44 years old 44 years old 44 years old 44 years old • Components of the system are in poor condition. • Units are very inefficient • All have exceeded useful life expectancy

  11. Plumbing Plumbing fixtures Do not meet current code requirements for water consumption. • Allowable: 1.6 gallons/flush (Existing fixtures: 3 gallons/flush) • Many of the fixtures do not meet ADA requirements • Fixtures are in poor to fair condition. • Water Heaters • Building Area ‘A’ (Good condition) • Building Areas ‘B’ and ‘C’ (Poor condition) • International Café Kitchen (Poor condition) • Area ‘D’ (Good condition) • Water Coolers • Poor condition • Do not meet ADA Standards • Many are damaged and are not operational

  12. Process | Design Committee Clint Alexander - GHS Teacher Erica Jenkins - Riverside Director Jim Brogan - GCPS IT Director Ralph Johnson - GCPS Ed Foundation Lori Buchanan - Sentara Director Heather Knight - Parent Gwyn Ciemniecki - GCPS HR Director Anne Lanan - GCPS Trans Director Rick Clemons - GCPS Superintendent Christi Lewis - GCPS Comm. Engagement Ken Cramer - Pastor Lighthouse Worship Heather Lucas - GCPS CFO Melissa Crawford - Chesapeake Bank VP Sam Markwith - GHS Graduate/Markwith Farms Kelly Dalton - ABG Teacher/Parent Wendy McIntyre - Parent Anne Ducey-Ortiz GC Planning Director Amy McLeod - Realtor/GYFL Vivian Eccleston - Student Jennifer Naquin - Parent Cassidy Evans - Student Elisa Nelson - Parent Holly Fleiger - Parent Elaine Norman - Retired Educator Beth Gibson - Parent Jessica North - GHS Media Specialist Mark Goodrich - NNSY Engineer Christina Parnell - Student John Gordon - Owner Chick-fil-A Dexter Parzanese - GHS Teacher Al Grant - NJROTC Steve Patton - GCPS Food Service Director Douglas Grossenbaugh - Canon GM Jason Perry - RCC Dustyn Hall - GHS Graduate John Phillips - Owner Phillips Energy Teresa Harmon - Parent Sheila Pillath - Gloucester YMCA Danielle Heaney - GHS Graduate Melanie Rapp Beale - Dominion Energy Heather Hogge - Parent Charles Records - GCPS School Board Kristy Hunter - GHS Health/PE Gary Rippel - Parent John Hutchinson - GCPS Asst. Supt. Kim Robins - Gazette Journal Chris Hutson - GC BOS Elizabeth Scott - GHS Teacher Donna Jemmison - GHS Teacher Cindi Sharp - Parent Scott Shorland - GCPS Construction Manager Brad Simmons - GCSO Sgt./Safety Roger Simpson - Canon Steve Smith - Peninsula Heating and Air Sherry Spring - GC Econ Development Director Brian Stewart - GC Engineer Patrice Stokes - GHS Counseling Leslie Sturtz - GHS Teacher Crystal Thompson - GHS Teacher Chuck Wagner - GCPS Asst. Supt. Darrell Warren - GC Sheriff Ward Warren - Pastor 1st Baptist Lyn Whitt - GHS Teacher Hutt Williams - RCC Gloria Williams - GC Chamber of Commerce

  13. Process • Design Workshop #1 | Idea Mining & Skills • Design Workshop #2 | Curriculum and Instructional Space

  14. Design Workshop | Wordle

  15. Process • Design Workshop #3 | Initial Conceptual Plan Review • Design Workshop #4 | Developed Plan Review

  16. Process • Design Workshop #5 | Further Conceptual Plan Review • Community Meeting No.1 | December 4, 2017 • Community Meeting No.2 | December 11, 2017

  17. Conceptual Floor Plans

  18. Existing Plan

  19. Conceptual Plans ConceptB ConceptA New Addition: 21,990 sq.ft. New Addition: 16,450 sq.ft.

  20. Conceptual Floor Plans | Concept A

  21. Conceptual Floor Plans | Concept A

  22. Conceptual Floor Plans | Concept A

  23. Conceptual Floor Plans | Concept A

  24. Conceptual Floor Plans | Concept A

  25. Conceptual Floor Plans | Concept B

  26. Conceptual Floor Plans | Concept B

  27. Conceptual Floor Plans | Concept A/B: 2-Phase Option - Phase 1

  28. Conceptual Floor Plans | Concept A/B: 2-Phase Option - Phase 2

  29. Conceptual Floor Plans | Concept A/B: 3-Phase Option - Phase 1

  30. Conceptual Floor Plans | Concept A/B: 3-Phase Option - Phase 2

  31. Conceptual Floor Plans | Concept A/B: 3-Phase Option - Phase 3

  32. Conceptual Site Plan

  33. Conceptual Site Plan

  34. Conceptual Site Plans | New

  35. Conceptual Site Plans | New Site Concept New

  36. Conceptual Site Plans | New Site Concept New

  37. Conceptual Site Plans | New Site Concept New

  38. Cost Models

  39. Master Plan Concept A | Cost Model 111,785sf 135,077sf 13,999sf 16,405sf Timeline: Design: 10-12 months Construction: 26-28 months

  40. Master Plan Concept A | Cost Model • New Construction: • 16,405sf • Light Renovation: • 111,785sf | HVAC, elec, lighting, finishes, technology, floors • Medium Renovation: • 135,077sf | light renovation plus wall relocation • Heavy Renovation: • 13,999sf | medium renovation plus slab work New Const Reno Proj Costs Total Project Cost Inflation • $70.2M • Jan 2020 Dollars • $270/sf • Light: $141/sf • Med: $157/sf • Heavy: $199/sf • Plus • Site Work • 30% Construction FF&E • Tech/AV • Survey • Testing • Commissioning • A/E Fees • Permits • Portable CR Rental • Contingency • 5.25% annually • Per DoE 2007-2017

  41. Master Plan Concept B | Cost Model 111,785sf 135,077sf 13,999sf 21,406sf Timeline: Design: 10-12 months Construction: 26-28 months

  42. Master Plan Concept B | Cost Model • New Construction: • 21,406sf • Light Renovation: • 111,785sf | HVAC, elec, lighting, finishes, technology, floors • Medium Renovation: • 135,077sf | light renovation plus wall relocation • Heavy Renovation: • 13,999sf | medium renovation plus slab work New Const Reno Proj Costs Total Project Cost Inflation • $71.9M • Jan 2020 Dollars • $270/sf • Light: $141/sf • Med: $157/sf • Heavy: $199/sf • Plus • Site Work • 30% Construction FF&E • Tech/AV • Survey • Testing • Commissioning • A/E Fees • Permits • Portable CR Rental • Contingency • 5.25% annually • Per DoE 2007-2017

  43. Master Plan Concept A/B: 2-Phase | Cost Model – Phase 1 • Highlights: • New main entry • Renovated A and C halls • New commons • Renovated media center • New drama room • All sitework 61,550sf. 106,408sf. 2,595sf. 16,405sf. Timeline: Design: 8-10 months Construction: 16-18 months

  44. Master Plan Concept A/B: 2-Phase | Cost Model – Phase 1 • New Construction: • 16,405sf • Light Renovation: • 61,550sf | HVAC, elec, lighting, finishes, technology, floors • Medium Renovation: • 106,408sf | light renovation plus wall relocation • Heavy Renovation: • 2,595sf | medium renovation plus slab work New Const Reno Proj Costs Total Project Cost Inflation • $52.7M • Jan 2020 Dollars • $270sf • Light: $141/sf • Med: $157/sf • Heavy: $199/sf • Plus • Site Work • 30% Construction FF&E • Tech/AV • Survey • Testing • Commissioning • A/E Fees • Permits • Portable CR Rental • Contingency • 5.25% annually • Per DoE 2007-2017

  45. Master Plan Concept A/B: 2-Phase | Cost Model – Phase 2 • Highlights: • Renovated D hall • Renovated gym and locker rooms • Classroom addition – D hall 50,235sf 28,669sf 11,404sf 5,001sf Timeline: Design: 6-8 months Construction: 10-12 months

  46. Master Plan Concept A/B: 2-Phase | Cost Model – Phase 2 • New Construction: • 5,001sf • Light Renovation: • 50,235sf | HVAC, elec, lighting, finishes, technology, floors • Medium Renovation: • 28,669sf | light renovation plus wall relocation • Heavy Renovation: • 11,404sf | medium renovation plus slab work New Const Reno Proj Costs Total Project Cost Inflation • $24.1M • Jan 2020 Dollars • $270/sf • Light: $141/sf • Med: $157/sf • Heavy: $199/sf • Plus • Minimal Site Work • 30% Construction FF&E • Tech/AV • Survey • Testing • Commissioning • A/E Fees • Permits • Portable CR Rental • Contingency • 5.25% annually • Per DoE 2007-2017

  47. Master Plan Concept A/B: 3-Phase | Cost Model – Phase 1 • Highlights: • New main entry • Renovated A hall • New commons • Renovated media center • New drama room • All sitework 55,096sf 58,113sf 2,057sf 16,405sf. Timeline: Design: 8-10 months Construction: 16-18 months

  48. Master Plan Concept A/B: 3-Phase | Cost Model – Phase 1 • New Construction: • 2,057sf • Light Renovation: • 55,096sf | HVAC, elec, lighting, finishes, technology, floors • Medium Renovation: • 58,113sf | light renovation plus wall relocation • Heavy Renovation: • 2,057sf | medium renovation plus slab work New Const Reno Proj Costs Total Project Cost Inflation • $41.8M • Jan 2020 Dollars • $270/sf • Light: $141/sf • Med: $157/sf • Heavy: $199/sf • Plus • Site Work • 30% Construction FF&E • Tech/AV • Survey • Testing • Commissioning • A/E Fees • Permits • Portable CR Rental • Contingency • 5.25% annually • Per DoE 2007-2017

  49. Master Plan Concept A/B: 3-Phase | Cost Model – Phase 2 • Highlights: • Renovated C hall 6,454sf 48,295sf 538sf 0sf Timeline: Design: 6-8 months Construction: 8-10 months

  50. Master Plan Concept A/B: 3-Phase | Cost Model – Phase 2 • New Construction: • 0sf • Light Renovation: • 6,454sf | HVAC, elec, lighting, finishes, technology, floors • Medium Renovation: • 48,295sf | light renovation plus wall relocation • Heavy Renovation: • 538sf | medium renovation plus slab work Reno Proj Costs Total Project Cost Inflation • $15.7M • Jan 2020 Dollars • Light: $141/sf • Med: $157/sf • Heavy: $199/sf • Plus • Minimal Site Work • 30% Construction FF&E • Tech/AV • Survey • Testing • Commissioning • A/E Fees • Permits • Portable CR Rental • Contingency • 5.25% annually • Per DoE 2007-2017

More Related