1 / 18

Dealing with Catastrophic Storm Issues January 2009 SE Missouri Ice Storm

Monday, January 26 Preparation and Advanced Warning. Quantum Weather predicts the possibility of ice storm in southern 1/3 of stateMobilized contractor resources and Missouri Valley resources to SEMO southMobilized 3 storm trailers and 1 Mobile Command Center. And it starts Tuesday, January 27 .

issac
Télécharger la présentation

Dealing with Catastrophic Storm Issues January 2009 SE Missouri Ice Storm

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. Dealing with Catastrophic Storm Issues January 2009 SE Missouri Ice Storm Missouri PSC Storm Workshop Presented by Dave Wakeman Manager, Distribution Operating AmerenUE

    2. Monday, January 26 Preparation and Advanced Warning Quantum Weather predicts the possibility of ice storm in southern 1/3 of state Mobilized contractor resources and Missouri Valley resources to SEMO south Mobilized 3 storm trailers and 1 Mobile Command Center

    3. And it starts Tuesday, January 27 At 4 a.m. only 800 customers outjust the beginning Major ice accumulation occurring throughout the day in SEMO south area Decision made to move all available AmerenUE resources to SEMO Outage numbers climb throughout the day Additional contractor resources procured 650 linemen and 350 tree trimmers engaged by end of day

    4. Significant Ice Formation Wednesday, January 28 Ice continues to buildoutage count over 36,000 in A.M. 6 counties in Bootheel are essentially without power Decision made to use Extensive Damage Recovery Method SEMO south divided into 8 work islands 1150 linemen and 450 tree trimmers engaged by end of day

    5. Missouri Counties Served by AmerenUE That Were Affected Cape Girardeau Dunklin Mississippi New Madrid Pemiscot Scott Stoddard

    6. Issues and responses Dense fog in morning caused black ice, generally dangerous driving conditions. Widespread damage - added storm trailers bringing the total to 8 Long repair times- Installed 3-2MVA generators to supply power for 2 towns

    7. Issues and responses Storm damage continues until the ice melts Then came the mud - needed farmers equip.

    9. Resource Summary Linemen 2400 Vegetation 555 Field Checking 160 Logistics 70 Stores 85 Other Support Personnel 730 Total Resources 4000

    11. Major Restoration Obstacles Extensive widespread severe damage Sub-transmission System Distribution System Logistics No power in the entire region for nearly 4 days Rural Arealimited infrastructure Supply Chain

    12. Widespread Damage Virtually 100% of AmerenUE customers in 6 counties without power 34 kV Sub-transmission System 25 circuits out of service and requiring major repair Portageville 71 (34kV) 30 miles long with 1 pole left standing 35 distribution substations without power 20 customer subs without power Distribution System 163 distribution circuits out of service

    13. Distribution System Many towns required significant re-builds

    14. Logistics

    15. Logistics Issues On Wednesday night we had rooms but they all lost power as the lineman were bedding down Logistics issues were significant enlisted help of a logistics company

    16. Logistics 15,500 hotel room nights 2300 alternative sleeping arrangementsbunk trailers, dorms, etc. 76,000 meals 1250+ loads of laundry 44 buses

    17. Accomplishments Portageville 71 Re-build 30 miles of line supplying 2 towns Completely re-built entire circuit in 3 days using 500 linemen Collaborated with SEMA and RECs to transition resources to Co-ops Participated in twice daily SEMA conference calls Provide daily restoration status updates

    18. Supply Chain Issues Comparison: SEMO Ice Storm vs. Sept 14, 2008 Storm (Hurricane Ike) SEMO Ice Storm 36,000 customers out Major Material Installed 3800 poles 7000 cross arms 700 transformers 1,440,000 ft of wire (273 miles) Sept 14, 2008 Wind Storm (Hurricane Ike) 161,000 customers out Major Material Installed 38 poles 295 cross arms 58 transformers 69,000 ft of wire

    19. Conclusions Emergency Plan designed to manage this contingency Logistics Plan was stretched to its limitsmany improvement opportunities identified Supply Chain process stretched to its limitmany improvement opportunities identified Preparation and advanced planning keys to success along with after-action review

More Related