1999 PACAF AOF CONFERENCE YOKOTA AIR BASE RUNWAY OVERLAY PROJECT • CAPT BRAD BAUGH, 374 OSS/OSAA
OVERVIEW • HISTORY • MONTHLY RUNWAY CLOSURES • CURRENT SCOPE OF PROJECT • CONSTRUCTION PLAN • OPERATIONAL PLAN • CHALLENGES • LESSONS LEARNED
HISTORY • BASE WAS CONSTRUCTED IN 1940/1 • U.S. TOOK OVER BASE IN 1945 • FIRST U.S. MAJOR CONSTRUCTION TO THE RUNWAY - 1956 • LAST MAJOR CONSTRUCTION IN 1992
HISTORY • RECENT AIRFIELD PROJECTS • WEST RAMP EXPANSION - 1995 • FILLED IN STUB PARKING SPOTS • DISPERSAL 8 RECONSTRUCTED - 1997/8 • WIDENED DISPERSAL • ADDED C-9 PARKING RAMP • SLAB REPLACMENT AND SHOULDER WORK ON WEST SIDE TAXIWAYS - 1998/9
MONTHLY RUNWAY CLOSURES • NECESSARY TO MAINTAIN RUNWAY OPERATIONS • TWO MAIN AVENUES OF WORK • CE SMALL REPAIRS • REQUIREMENTS CONTRACT
MONTHLY RUNWAY CLOSURES • CE SMALL REPAIRS • “BUBBLE GUM” FIX • SET 45 • EPOXY
MONTHLY RUNWAY CLOSURES • REQUIREMENTS CONTRACT • SLAB REPLACEMENT • JET CONCRETE
MONTHLY RUNWAY CLOSURES • COMMUNICATION IS KEY • WEEKLY MEETINGS WITH CE • PRE/POST CLOSURE AIRFIELD INSPECTIONS • CHALLENGES • AIRCRAFT OPERATIONS • EXERCISES AND DV MOVEMENTS
CURRENT SCOPE OF PROJECT • GOJ FUNDED PROJECT • 200 DAY PROJECT SLATED TO START OCT 00 • OVERLAY ENTIRE RUNWAY TO INCLUDE OVERRUNS • INSTALL NEW LIGHTING SYSTEMS • 20 PERCENT DESIGNED
CONSTRUCTION PLAN • INJECT SUB-SURFACE OF RUNWAY • OVERLAY ONE HALF OF RUNWAY AT A TIME • GRINDING REQUIRED • ALTERNATE ROWS OF SLABS NORTH AND SOUTH DOWN RUNWAY • ALLOWS CONTRACTOR TO SET UP PAVERS ON NEW CONCRETE
CONSTRUCTION PLAN 1 2 1 2 1 2 1 2 1 2 1/2 RUNWAY CONSTRUCTION SEQUENCE
CONSTRUCTION PLAN • HAUL ROUTES FROM OVERRUNS • CONCRETE DELIVERED FROM OFF BASE
OPERATIONAL PLAN • C-130, C-17, C-21 AND HELICOPTER OPERATIONS • HALF RUNWAY OPERATIONS • 4500 FEET OF USABLE RUNWAY • BLAST FENCE AT MID-FIELD • DISPLACED THRESHOLD • ILS INOPERATIVE
OPERATIONAL PLAN • HALF RUNWAY OPERATIONS CONT • DEPART AWAY FROM FENCE • ARRIVE OVER FENCE
OPERATIONAL PLAN • EAST PARALLEL RUNWAY • C-130 AND C-21 OPERATIONS • 6000’ LENGTH, 100’ WIDTH • TACAN APPROACHES
CHALLENGES • CULTURAL • COMMUNICATION • LANGUAGE • INTERPRETING U.S. REGULATORY GUIDANCE • JAPANESE VS U.S. PATIENCE • FISCAL YEAR OFFSET
CHALLENGES • CONTINGENCY - 5027 SCENARIO • RECONSTITUTE THE RUNWAY • REQUEST 9000’ FEET IN 7 DAYS • TPFDD FLOW EFFECT
CHALLENGES • OPERATIONAL • SAFETY IS PARAMOUNT • FENCE AT MID-FIELD • OBSTACLES AND CLIMB GRADIENT ON EAST PARALLEL RUNWAY • PILOT EXPERIENCE LEVEL
CHALLENGES • AIRFIELD OPERATIONS • WAIVER PACKAGE FOR EAST PARALLEL RUNWAY • ENSURING DESIGN MEETS SPECIFICATIONS • TEMPORARY LIGHTING AND MARKING • FOD PROBLEMS • NOTAMS
LESSONS LEARNED • CLEARLY DEFINE REQUIREMENTS • NICE TO HAVES MAY NOT BE JUSTIFIABLE • CENTRAL POINT OF CONTACT • COMMUNICATE CLEARLY • CONTINUITY • CE NEEDS TO LEARN THEIR AFIs • NOTHING NEW