An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 1999 PACAF AOF CONFERENCE YOKOTA AIR BASE RUNWAY OVERLAY PROJECT • CAPT BRAD BAUGH, 374 OSS/OSAA

  2. OVERVIEW • HISTORY • MONTHLY RUNWAY CLOSURES • CURRENT SCOPE OF PROJECT • CONSTRUCTION PLAN • OPERATIONAL PLAN • CHALLENGES • LESSONS LEARNED

  3. YOKOTA AIR BASE

  4. HISTORY • BASE WAS CONSTRUCTED IN 1940/1 • U.S. TOOK OVER BASE IN 1945 • FIRST U.S. MAJOR CONSTRUCTION TO THE RUNWAY - 1956 • LAST MAJOR CONSTRUCTION IN 1992

  5. HISTORY • RECENT AIRFIELD PROJECTS • WEST RAMP EXPANSION - 1995 • FILLED IN STUB PARKING SPOTS • DISPERSAL 8 RECONSTRUCTED - 1997/8 • WIDENED DISPERSAL • ADDED C-9 PARKING RAMP • SLAB REPLACMENT AND SHOULDER WORK ON WEST SIDE TAXIWAYS - 1998/9

  6. MONTHLY RUNWAY CLOSURES • NECESSARY TO MAINTAIN RUNWAY OPERATIONS • TWO MAIN AVENUES OF WORK • CE SMALL REPAIRS • REQUIREMENTS CONTRACT

  7. MONTHLY RUNWAY CLOSURES • CE SMALL REPAIRS • “BUBBLE GUM” FIX • SET 45 • EPOXY

  8. MONTHLY RUNWAY CLOSURES • REQUIREMENTS CONTRACT • SLAB REPLACEMENT • JET CONCRETE

  9. MONTHLY RUNWAY CLOSURES • COMMUNICATION IS KEY • WEEKLY MEETINGS WITH CE • PRE/POST CLOSURE AIRFIELD INSPECTIONS • CHALLENGES • AIRCRAFT OPERATIONS • EXERCISES AND DV MOVEMENTS

  10. CURRENT SCOPE OF PROJECT • GOJ FUNDED PROJECT • 200 DAY PROJECT SLATED TO START OCT 00 • OVERLAY ENTIRE RUNWAY TO INCLUDE OVERRUNS • INSTALL NEW LIGHTING SYSTEMS • 20 PERCENT DESIGNED

  11. CONSTRUCTION PLAN • INJECT SUB-SURFACE OF RUNWAY • OVERLAY ONE HALF OF RUNWAY AT A TIME • GRINDING REQUIRED • ALTERNATE ROWS OF SLABS NORTH AND SOUTH DOWN RUNWAY • ALLOWS CONTRACTOR TO SET UP PAVERS ON NEW CONCRETE

  12. CONSTRUCTION PLAN 1 2 1 2 1 2 1 2 1 2 1/2 RUNWAY CONSTRUCTION SEQUENCE

  13. CONSTRUCTION PLAN • HAUL ROUTES FROM OVERRUNS • CONCRETE DELIVERED FROM OFF BASE

  14. OPERATIONAL PLAN • C-130, C-17, C-21 AND HELICOPTER OPERATIONS • HALF RUNWAY OPERATIONS • 4500 FEET OF USABLE RUNWAY • BLAST FENCE AT MID-FIELD • DISPLACED THRESHOLD • ILS INOPERATIVE

  15. OPERATIONAL PLAN • HALF RUNWAY OPERATIONS CONT • DEPART AWAY FROM FENCE • ARRIVE OVER FENCE

  16. OPERATIONAL PLAN • EAST PARALLEL RUNWAY • C-130 AND C-21 OPERATIONS • 6000’ LENGTH, 100’ WIDTH • TACAN APPROACHES

  17. CHALLENGES • CULTURAL • COMMUNICATION • LANGUAGE • INTERPRETING U.S. REGULATORY GUIDANCE • JAPANESE VS U.S. PATIENCE • FISCAL YEAR OFFSET

  18. CHALLENGES • CONTINGENCY - 5027 SCENARIO • RECONSTITUTE THE RUNWAY • REQUEST 9000’ FEET IN 7 DAYS • TPFDD FLOW EFFECT

  19. CHALLENGES • OPERATIONAL • SAFETY IS PARAMOUNT • FENCE AT MID-FIELD • OBSTACLES AND CLIMB GRADIENT ON EAST PARALLEL RUNWAY • PILOT EXPERIENCE LEVEL

  20. CHALLENGES • AIRFIELD OPERATIONS • WAIVER PACKAGE FOR EAST PARALLEL RUNWAY • ENSURING DESIGN MEETS SPECIFICATIONS • TEMPORARY LIGHTING AND MARKING • FOD PROBLEMS • NOTAMS

  21. LESSONS LEARNED • CLEARLY DEFINE REQUIREMENTS • NICE TO HAVES MAY NOT BE JUSTIFIABLE • CENTRAL POINT OF CONTACT • COMMUNICATE CLEARLY • CONTINUITY • CE NEEDS TO LEARN THEIR AFIs • NOTHING NEW