Management Plan. : is designed to add a new generation wide field bolometer camera to the JCMT. GOAL: To maximize the science yield in the context of future facilities. What is the minimum time to results?. Estimate 6 years

Télécharger la présentation

Management Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Management Plan : is designed to add a new generation wide field bolometer camera to the JCMT GOAL:To maximize the science yield in the context of future facilities What is the minimum time to results? Estimate 6 years as the minimum possible time to results with realistic risk management

  2. Contributing organisations • Key organizations: • ATC Key skills and experience in major projects including SCUBA • NIST The clear leader in TES technology, SQUID Muxes and control electronics • U of E Demonstrated expertise in Si micro-machining + technology development in the UK • QMW Key technologies and expertise, in filters, FTS testing, window materials, detector testing • JAC The customer plus key experience with SCUBA

  3. Key Staff Positions • Key positions: • Project Manager Internationally distributed project - good project management skills plus technical contribution • Project Scientist Active mm/submm observer and scientist with “customer view point” and good laboratory skills

  4. Key Staff Positions • Key positions: • Systems Engineer Experienced project/systems engineer to manage all the technical complexity of the project from capturing requirements to delivering the verified instrument • Instrument Scientist Good laboratory scientist, ideally with clean room experience

  5. Outline of WP responsibilities

  6. SCUBA 2 Array Development • development supported by PPARC grant (assumed) • and SCUBA 2project • funds

  7. Project Plan for Technology Development • NB Science • Instrument • not planned • in yet

  8. Detector development ~ 50% of total Software effort ~ 30% of total Technology Development Cost and Effort

  9. OUTLINE OF PROJECT RESOURCES (Estimated on limited work)

  10. Cost per pixel!