Linac (WBS 1.2.2) Long-Lead ProcurementEric Lind BongMay 21, 2003 • Descriptions of Procurements • Acquisition Plans • Schedule for PED to Support FY2005 Procurements • Summary Plan for Remainder of WBS • CONSTRUCTION AND CRITICAL PATH ISSUES Eric Bong, SLAC
LCLS Accelerator and Compressor Schematic 250 MeV z 0.19 mm 1.8 % 4.54 GeV z 0.022 mm 0.76 % 14.35 GeV z 0.022 mm 0.02 % 7 MeV z 0.83 mm 0.2 % 150 MeV z 0.83 mm 0.10 % Linac-X L =0.6 m rf=180 rf gun Linac-1 L =9 m rf = -38° Linac-2 L =330 m rf = -43° Linac-3 L =550 m rf = -10° new Linac-0 L =6 m undulator L =120 m 21-1b 21-1d 21-3b 24-6d 25-1a 30-8c X BC-1 L =6 m R56= -36 mm BC-2 L =22 m R56= -22 mm DL-1 L =12 m R56 0 DL-2 L =66 m R56 = 0 SLAC linac tunnel undulator hall Eric Bong, SLAC
Linac BC1 Area Long Lead Procurement Items Slide Showing L1& BC1 Schematic Diagram Notes positions of X-Band Structure Notes Position of BC1 Bend Magnets • BC1 Chicane • X-Band Structure at Entrance • Entire System Required as Long Lead Procurement • BC1 Bend Magnets • Limited Design and Fabrication Manpower Requires Inclusion as Long Lead Procurement Eric Bong, SLAC
Linac BC2 Area Long Lead Procurement Items • BC2 Chicane • Superconducting Wiggler at Entrance • Cold Mass and Cryostat required as Long Lead Procurement Items • BC2 Bend Magnets • Limited Design and Fabrication Manpower Requires Inclusion as Long Lead Procurement Eric Bong, SLAC
Linac X-Band System Components • X-Band Klystron • Modulator • Low Level RF • Waveguide Distribution • Structure Eric Bong, SLAC
Linac X-Band System Acquisition Plan • X-band system fabricated and assembled at SLAC • Standard components purchased from vendors when available Eric Bong, SLAC
Linac X-Band System Time LineDesign, Long Lead Procurement, Construction, Installation, Laser Commissioning Eric Bong, SLAC
Linac Superconducting Wiggler • Cold Mass • Cryostat • Quench Detection Circuit Refe… Eric Bong, SLAC
Superconducting Wiggler Acquisition Plan • Cold Mass, Cryostat & QD Acquired from single vendor • SLAC provides Engineering Analysis and Parameters • Vendor Fabricates to SLAC Engineering Parameters • Vendor Provides Detail Design Eric Bong, SLAC
Superconducting Wiggler Time LineDesign, Long Lead Procurement, Construction, Installation, Laser Commissioning Eric Bong, SLAC
Bunch Compressor Chicane Bend Magnets • BC1 Bend Magnets • Length: 20 cm • Field: 3.3 kG • Similar Existing SLAC Design • BC2 Bend Magnets • Length: 50 cm • Field: 9.5 kG • Similar Existing SLAC Design Eric Bong, SLAC
BC Bend Magnets Acquisition Plan Bend Magnet Design and Fabrication at SLAC Long Lead Procurement Required Due to Manpower Limitations Eric Bong, SLAC
BC Bend Magnet Time LineDesign, Long Lead Procurement, Construction, Installation, Laser Commissioning Eric Bong, SLAC
LCLS Linac Summary by AreaDesign, Long Lead Procurement, Construction, Installation, Laser Commissioning Eric Bong, SLAC
LCLS Linac WBS SummaryDesign, Long Lead Procurement, Construction, Installation, Laser Commissioning Eric Bong, SLAC