1 / 5

6.4 Estimate Activity Duration

Monitor. Initiation. Planning. Execution. Close. Control. 6.4 Estimate Activity Duration. The process of approximating the number of work periods needed to complete individual activities with the assigned or estimated resources

jbinkley
Télécharger la présentation

6.4 Estimate Activity Duration

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Monitor Initiation Planning Execution Close Control 6.4 Estimate Activity Duration • The process of approximating the number of work periods needed to complete individual activities with the assigned or estimated resources • Previous experience in the type of project and activities being estimated greatly helps with the accuracy of duration estimates • Duration is a function of work effort and resources • Most project management software can perform this function • Occurs during the Planning Phase Adapted from PMBOK 4th Edition

  2. 6.4 Estimate Activity Duration Inputs to Estimate Activity Duration Activity list and attributes Activity Resource requirements and estimates Resource Calendars Project Scope Statement Productivity metrics and estimating data Tools and techniques to Estimate Activity Duration Reserve Analysis Analogous Estimating Expert Judgement Parametric Estimating Three-Point Estimating Adapted from PMBOK 4th Edition

  3. 6.4 Estimate Activity Duration Analogous Estimating Develops duration estimates based on previous projects with similar size, risk and complexity Relies heavily of expert judgement and previous experience Less costly and less time consuming than other methods Least accurate Most common form of duration estimating Parametric Estimating Duration is quantified by multiplying the quantity of work by the labour hours required Relies on published estimating data Common in Construction Monitor Initiation Planning Execution Close Control Adapted from PMBOK 4th Edition

  4. 6.4 Estimate Activity Duration Three-Point Estimates - PERT Calculates the Expected activity duration based on the weighted average of the Most Likely, Optimistic and Pessimistic estimates Often more accurate than other methods and quantified range of uncertainty Reserve Analysis Inclusion of contingency Can be calculated for each activity Can be calculated for entire project Often a percentage based on risk or complexity Monitor Initiation Planning Execution Close Control Adapted from PMBOK 4th Edition

  5. 6.4 Estimate Activity Duration The major output of this process Activity Duration Estimates Draft or High Level Project Duration Estimate Often include some form of range of possible results Most common form of range is plus or minus - eg 2 weeks +/- 2 days – the activity could take between 8 and 12 days 3 weeks +/- 30% - the activity could take between 2 weeks and 4 weeks Monitor Initiation Planning Execution Close Control Adapted from PMBOK 4th Edition

More Related