An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. ERTMS Strategy for the deployment of ERTMS, towards the implementation of version 3.0.0.

    2. 2 Corridor A is by far the most heavily utilised rail freight axis in Europe ERTMS is required for seamless cross-border rail traffic

    3. 3 Different deployment solutions for ETCS allow the consideration of existing infrastructure as well as required operation conditions

    4. 4 Baseline 3 consitutes the most economical and compatible ETCS deployment concept from both trackside and vehicle perspective

    5. 5 According to existing infrastructure and capacity / speed require- ments, Corridor A infrastructure managers opted for Baseline 3

    6. 6 Approximately 30% of the German part of Corridor A are planned to be equipped with ETCS L1LS

    7. 7 The cost differential achievable by applying ETCS L1 LS to part of the German segmant of Corridor A amounts to app. 500 600 Mill. Euro

    8. 8 In order to ensure the overall timeline on Corridor A, a resolute course of action will be followed for the German part

    9. 9

    10. 10

    11. 11

    12. 12 Realising ETCS trackside installations based on SRS 3.0.0 reduces necessary investments for Corridor A by approximately 620 m