250 likes | 344 Vues
Civil Engineering and Services - drawings for CDR - CDR chapter. J.Osborne and M.Gastal for CES WG. CE Drawings for CDR. 11 drawings have been circulated for comments and are available at: http://indico.cern.ch/conferenceDisplay.py?confId= 73959
E N D
Civil Engineering and Services - drawings for CDR- CDR chapter J.Osborne and M.Gastal for CES WG
CE Drawings for CDR • 11 drawings have been circulated for comments and are available at: http://indico.cern.ch/conferenceDisplay.py?confId=73959 • These drawings need to be frozen immediately if we are to meet the deadline for CDR and costing exercises • Changes could be made later during the Technical Design phase
Comments • Most important drawing for costing • Tunnel length includes all tunnels • Site length is the amount of land needed to build CLIC • Colour code: Purple interaction region Blue BDS Green injection complex Dark pink 500Gev option Light pink 3TeV option
Comments • Cross section has been increased from 4.5m to 5.6m • 5.6m is the standard size for European subways • Power converter community requested a lot more space => increase diameter of tunnel • Use of transversal ventilation • CV pipes in slab are now isolated from machine by a compressible filler • Cable trays are not earmarked for now
Comments • Such shaft will be found every 5 kms • Compared to the last version, the cavern was turned around • 2 transport tunnels were added at the request of Transport Group
Comments • Cut and cover tunnels • No slope in bended region of e- injector • Different slopes for e+ and e-
Comments • Turnaround region every 878m • The size of the facility cavern has increased significantly to host power converter/CV/ EL equipment • Approved by user : BERNARD JEANNERET on 22-SEP-2010 Comments : the turn-around line and the dump cavern are still notional , must be reworked in the TDR phase
Comments • Red lines set-out the limit of CERN land • Drive beam injection line to be added
Comments • Typicalcross section for 9m diameter shaft found every 5 km • Based on LHC design
Comments • Bypass tunnel now out of the volume of the detector assembly cavern • Shielding doors to remain as a place holder, detector could be self shielded • Wall alongside shielding doors have to be flat • Safety galleries for both caverns have been added • 2x80t cranes on surface + 2x20t cranes underground, based on CMS site
Comments • Overview of InjectionComplex • 5m cut and cover tunnels • Missing information on distance between access shafts • Drive beam injector building 2.5km long, 30m wide • None of these buildings existed for previous costing exercise • Missing central machine cooling tower - water not coming from lake anymore for CDR option. • Both options will still be examined for TDR • Surface buildings for IR based on CMS
Comments • Many changes were introduced but design is now converging
Comments • BDS length was changed because the tunnel got wider. If we want to maintain a 2m thick shielding at the Beam dump cavern, the BDS has to become longer • No other changes can be envisaged for the CDR
Conclusions and roadmap • CES meetings on 29 Sept and 11 October to : • Review CDR CES chapter • HVAC section difficult to finalise because of heat loads uncertainties • CDR draft for CES Chapter here : • \\cern.ch\dfs\Workspaces\i\ILC\CLIC\CDR\CES_Chapter • CES Costing planned for end of October • Agenda for CES scheduling accelerator working group (9) at IWLC2010 progressing well