An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Civil Engineering and Services - drawings for CDR- CDR chapter J.Osborne and M.Gastal for CES WG

  2. CE Drawings for CDR • 11 drawings have been circulated for comments and are available at: http://indico.cern.ch/conferenceDisplay.py?confId=73959 • These drawings need to be frozen immediately if we are to meet the deadline for CDR and costing exercises • Changes could be made later during the Technical Design phase

  3. Comments • Most important drawing for costing • Tunnel length includes all tunnels • Site length is the amount of land needed to build CLIC • Colour code: Purple interaction region Blue BDS Green injection complex Dark pink 500Gev option Light pink 3TeV option

  4. Comments • Cross section has been increased from 4.5m to 5.6m • 5.6m is the standard size for European subways • Power converter community requested a lot more space => increase diameter of tunnel • Use of transversal ventilation • CV pipes in slab are now isolated from machine by a compressible filler • Cable trays are not earmarked for now

  5. Comments • Such shaft will be found every 5 kms • Compared to the last version, the cavern was turned around • 2 transport tunnels were added at the request of Transport Group

  6. Comments • Cut and cover tunnels • No slope in bended region of e- injector • Different slopes for e+ and e-

  7. Comments • Turnaround region every 878m • The size of the facility cavern has increased significantly to host power converter/CV/ EL equipment • Approved by user : BERNARD JEANNERET on 22-SEP-2010   Comments : the turn-around line and the dump cavern are still notional , must be reworked in the TDR phase

  8. Comments • Red lines set-out the limit of CERN land • Drive beam injection line to be added

  9. Comments • Typicalcross section for 9m diameter shaft found every 5 km • Based on LHC design

  10. Comments • Bypass tunnel now out of the volume of the detector assembly cavern • Shielding doors to remain as a place holder, detector could be self shielded • Wall alongside shielding doors have to be flat • Safety galleries for both caverns have been added • 2x80t cranes on surface + 2x20t cranes underground, based on CMS site

  11. Comments • Overview of InjectionComplex • 5m cut and cover tunnels • Missing information on distance between access shafts • Drive beam injector building 2.5km long, 30m wide • None of these buildings existed for previous costing exercise • Missing central machine cooling tower - water not coming from lake anymore for CDR option. • Both options will still be examined for TDR • Surface buildings for IR based on CMS

  12. Comments • Many changes were introduced but design is now converging

  13. Comments • BDS length was changed because the tunnel got wider. If we want to maintain a 2m thick shielding at the Beam dump cavern, the BDS has to become longer • No other changes can be envisaged for the CDR

  14. Conclusions and roadmap • CES meetings on 29 Sept and 11 October to : • Review CDR CES chapter • HVAC section difficult to finalise because of heat loads uncertainties • CDR draft for CES Chapter here : • \\cern.ch\dfs\Workspaces\i\ILC\CLIC\CDR\CES_Chapter • CES Costing planned for end of October • Agenda for CES scheduling accelerator working group (9) at IWLC2010 progressing well