1 / 16

CRYOGENICS PERFORMANCE AND OPERATION

CRYOGENICS PERFORMANCE AND OPERATION. L. Serio , on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel. Contents. Introduction on cooling down and commissioning time Tuning loops adjustment & CV910 puppets – acquired knowledge and expected improvement

jrobie
Télécharger la présentation

CRYOGENICS PERFORMANCE AND OPERATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel

  2. Contents • Introduction on cooling down and commissioning time • Tuning loops adjustment & CV910 puppets – acquired knowledge and expected improvement • Measured recovery time after quenches vs. theoretical expectations. DFBs filling • Availability study for cryogenic system - can system components or related services be improved to maximize overall availability • Improvement of He quality with new compressor. Translation to other sectors • Vacuum minor leaks' impact on 1.9 K stability - improved strategy for GLPT in 45/81 • Time to repair a fault occurring just before the week-end: is it adequate for running LHC? • Is recovery time after problems resource dependant? If so, can extra resource be made available when required eg weekends, nights? • Interlocks: New PIC-Cryo channels • Is it likely that if multiple sectors are commissioned, a cryo problem in one sector will not affect other sectors – thus allowing effort to be put elsewhere?

  3. Cool-down Global tuning And DFBs commissioning Powering (Big gain expected) (2-3 wks w.r.t 9 wks)

  4. LHC Cryogenics: duration of cool-down phases 9 d Design LHC 7-8 Final 21 d 80 K 14 d Sketches intended to illustrate achievements and ultimate expectations S. Claudet - Jul’07 3 d Design LHC 7-8 Final 14 d 20 K 7 d 1 d Design LHC 7-8 Final 14 d 4.5 K 3 d 1 d Design LHC 7-8 Final 21 d 1.9 K Excluding ELQA or extra-works : 4 d 14 d / 2 wks 70 d / 10 wks Design LHC 7-8 Final ELQA Total 28 d / 4 wks

  5. Data for LHC scheduling purposes • First time a given cryoplant type is used: 4-5 , 8-1 , 3-4 , 7-8: 8 wks + ELQA • Second time a given cryoplant type is used: 5-6 , 6-7: 6 wks + ELQA • For 2008 onwards: 4-5 , 3-4: 4 wks + ELQA • Warm-up: Complete sector: 4 wks the first time (Design: 2 wks) QRL + some cells: 2 wks Proposed durations with expected learning effects to be checked autumn 2007 S. Claudet - Jul’07

  6. Tuning loop adjustments • June 18: Simultaneous, sawtooth ramping of D2 and Q4

  7. Tuning loop adjustments

  8. Valves: Flow caracteristics Large sensitivity gain Installed R ~ 25 New R ~ 100

  9. Availability: From 7-8 to others Cryo Maintain ARC: 66% (Since 1st June) Cryo Maintain LSS: 85% (Since 1st May) DFBMs DFBAs Target LSS: 90% (incl. time lost for quench recovery) Target ARC: 80% (incl. time lost for quench recovery)

  10. Quench recovery for one quadrupole • Quench 720 A => TTregulation + 20 mK • Quench 2000 A => TTregulation + 200 mK & 5 minutes for Cryostart (2 K) • Quench 6500 A => TTregulation + 1.3 K & ~ 40 minutes for Cryostart (< 2 K) • New : Quench 2 x 6500 A => TTregul + 4 K & 2h30 for Cryostart (< 2 K) • => No effect on cold compressors • NB : Cryostart recovery time not yet optimised (presence output limit high on JT valve to limit overshoot)

  11. Recovery Time after Limited Resistive Transitions • More than 14 cells or full sector  recovery up to 48 hours • In case of fast discharge (even w/o quench)  2 h recovery (heating due to eddy currents).

  12. Interlocks: New PIC-Cryo channels • For operation reasons a cryo-start signal for 60 Amps will be implemented taking into account beam screen temperature (heat intercept) and eventually the thermal screen temperature • Details to be discussed with system owner and PIC team • To be implemented already for sector 4-5

  13. Helium quality for distribution • Improvement of He quality with for other refrigerators (sectors) • Problem only for ex-LEP cryoplants from Air Liquide for which the sub-cooler was just made for isothermal refrigeration (LEP) and not for non-isothermal refrigeration (LHC) • Problem identified Autumn’06 • Proposal received for modification, but no agreed yet • The change of refrigerator did not show big impact on commissioning. Major gain to be expected in pseudo liquefaction mode when re-filling after a stop

  14. Vacuum minor leaks • No major problems for stability /cooling power with the levels accepted in sector 7-8 • Can have (depending on the level) some impact on recovery time • More problematic is the leak (no connection) of the Y tube in the bayonet heat exchanger • Can still function with adjacent cell but increase in recovery of cryo start conditions (cooldown)

  15. Time to repair a fault outside working hours • Time to repair a fault occurring just before the week-end: is it adequate for running LHC? => We are not running the LHC we are commissioning it and cryogenics is part of the commissioning … • Is recovery time after problems resource dependant? If so, can extra resource be made available when required eg weekends, nights? • Efforts put on control logic (long term) rather than on manpower (short term) • Furthermore resources need to be trained or be expert in the domain for most of the problems encountered • Efforts and intervention are anyway already performed during the weekends and nights even if you do not realize it • Is it likely that if multiple sectors are commissioned, a cryo problem in one sector will not affect other sectors – thus allowing effort to be put elsewhere? =>YES, machines and teams independent

More Related