Microsoft's Project Alluvion involves a four-phase data center development spanning 154 acres with a total investment of $1,126,218,000. The first phase includes a 1,165,364 sq ft building and 84 employment opportunities. Potential infrastructure improvements include road upgrades and water/sewer enhancements. The project also involves relocating power lines, installing fiber optics, and constructing a public safety facility. Scheduled phases include plan review, grading, construction of Phase 1, and subsequent phases.
E N D
Incentives & Infrastructure • Estimated incentives and Infrastructure cost: $87,000,000 • We will have a Development Agreement with Microsoft that will also have a minimum assessment agreement requiring a minimum property valuation of $255,000,000 at the end of Phase IV
Project Description • Four phase data center • Area: 154 acres • Total investment: $1,126,218,000 • Total building size: 1,165,364 square feet • Total employment: 84
Potential Infrastructure Improvements • South 8th Street (old Army Post Rd to County Line Rd) • Pine Avenue to new Army Post Road
Potential Infrastructure Improvements Continued • Pine Avenue upgrades (eastern Corporate Limits to South 8th Street) • Maffitt Road/County Line Road connection (South Veterans’ Parkway to County Line Road) • County Line Road connector to MaffittRoad extension
Water & Sewer • Water line distribution/storage upgrades • Sanitary sewer line upgrades
Services • Relocation of MidAmerican power line • Fiber optic conduit/fiber line installation • Public Safety Facility (to be constructed/equipped as part of TIF District at a date to be determined)
Schedule • Review plans (Phase I only) • Grading • Construction of Phase 1 • Open Phase 1 • Future Phases