Comprehensive Implementation of Watershed Management in Namakkal District
The full implementation phase of the watershed project in Namakkal District (Watershed Code: 4B1B3b3a1 & 4B1B3b3a2) under NABARD-WDF has achieved significant results. Key accomplishments include the completion of 1,440 cum of water absorption trenches, 1,203 cum of contour trenches, 66 meters of stone gully plugs, and the establishment of loose boulder structures. The total expenditure amounts to Rs. 1,38,044. These interventions substantially enhance water conservation and soil management, addressing environmental challenges in the region.
Comprehensive Implementation of Watershed Management in Namakkal District
E N D
Presentation Transcript
NABARD – WDFSeventhipatty & vadavathur watershedNamakkal - District Full implementation phaseWatershed Code No:4B1B3b3a1 &4B1B3b3a2 PFA - HEALDS
WATER ABSORPTION TRENCHTotal cum : 1440 Total amount :Rs 60746Work completed : 1050 cum Balance work :390 cum WATER ABSORPTION TRENCH (BEFORE) WATER ABSORPTION TRENCH (AFTER)
WATER ABSORPTION TRENCH WATER ABSORPTION TRENCH (BEFORE) WATER ABSORPTION TRENCH (AFTER)
CONTOUR TRENCH Total cum :1203Total amount : 50749Contour trench work is completed CONTOUR TRENCH (BEFORE) CONTOUR TRENCH (AFTER)
CONTOUR TRENCH CONTOUR TRENCH (BEFORE) CONTOUR TRENCH (AFTER)
STONE GULLY PLUGSTotal Rm : 66Total amount : 21204Stone Gully plugs work is completed STONE GULLY PLUGS (BEFORE) STONE GULLY PLUGS (AFTER)
STONE GULLY PLUGS STONE GULLY PLUGS (BEFORE) STONE GULLY PLUGS (AFTER)
LOOSE BOULDER STRUCTURE LOOSE BOULDERS STRUCTURE (BEFORE) LOOSE BOULDERS STRUCTURE (AFTER)
LOOSE BOULDER STRUCTURETotal cum : 90Total amount : 29645Loose boulder structure is completed LOOSE BOULDER STRUCTURE (BEFORE) LOOSE BOULDER STRUCTURE (AFTER)