The 34th ALICE DCS Workshop proposes a significant upgrade to the High-Level Trigger (HLT) system, aiming to double the computing power from 150 kW to 300 kW. This enhancement requires careful management of power distribution, with all Y-racks on UPS and all X,Z racks on EXD. The proposal estimates approximately 9 kW per mono rack, with a maximum current of 30A per phase, necessitating perfect balance to avoid overloading. Additionally, the workshop addresses unresolved issues with old cabling and fan failures, emphasizing the need for timely solutions.
Upgrade Proposal for HLT Power Enhancement in 34th ALICE DCS Workshop
E N D
Presentation Transcript
HLT power (CR2) 34th ALICE DCS Workshop • Due to RCU upgrade HLT expects to double computing power • 150kW -> 300kW • Cannot be all UPS (will compete with DAQ) • Proposal HLT: • All Y-racks on UPS (17) • All X,Z-racks on EXD (18) • 5 Z rack as reserve • Estimate per rack: ~9kW (mono) • ~ 15A per phase -> 30A per ‘depart’ • close to limit (32A), needs ‘perfect’ balance over phases • To be discussed with EL
CR2 – alimente depuis nouveau EOD2/20 X01 ( - - ) Y01 (- - ) Z01 ( - - ) X02 ( - - ) Y02 (y01) Z02 ( - - ) 208/20 Y03 (y02) Z03 (z01) X03 ( - - ) 217/20 Y04 (y03) X04 (- - ) Z04 (z02) 209/20 X05 (- - ) Y05 (y04) Z05 (z03) 218/20 X06 ( - - ) Y06 (y05) Z06 (z04) 210/20 X07 (EXD2/20) Y07 (y06) Z07 (z05) 219/20 X08 (x01) Z08 (z06) Y08 (y07) 203/20 211/20 X09 (x02) Y09 (y08) Z09 (z07) 220/20 X10 (x03) Y10 (y09) Z10 (z08) 204/20 212/20 Y11 (y10) X11 (x04) Z11 ( - - ) X12 (x05) Z12 ( - - ) Y12 (y11) 205/20 213/20 Y13 (y12) X13 (x06) Z13 ( - - ) X14 (x07) Z14 (z09) Y14 (y13) 206/20 214/20 221/20 X15 (x08) Y15 (y14) Z15 (z10) Y16 (y15) Z16 (z11) X16 (x09) 207/20 Y17 (y16) X17 (x10) Z17 (z12) 215/20 222/20 Y18 (y17) Z18 (z13)
HLT power (CR2) 34th ALICE DCS Workshop • New cables from new switchboard to new splitter box installed • Splitter boxes not yet installed (but prepared) • Old cabling (EXD, Hazemeyer) still in place
Turbines UX racks 34th ALICE DCS Workshop • Many failures • Fan gets loose from motor • Will need to order 100 pairs • Perform exchange close to racks (limit transport) • Will do a ‘test exchange’ with Fred to estimate time and place needed