SVHS Construction Update March, 2009. March, 2009. Placement of Construction office portable by baseball field Begin site preparation in pool area Disassemble existing Press Box. April, 2009. Begin construction of new Press Box Start excavation work for Ag Barn
E N D
SVHS Construction Update March, 2009
March, 2009 • Placement of Construction office portable by baseball field • Begin site preparation in pool area • Disassemble existing Press Box
April, 2009 • Begin construction of new Press Box • Start excavation work for Ag Barn • Begin construction of new parking areas • Pool and stairs on back of existing gym
May, 2009 • Begin Construction on new Ag Barn • Continue construction on Press Box • Continue construction on new parking areas
June, 2009 • Continue construction on new parking areas • Continue construction on new Ag Barn • Continue construction on Press Box • Start construction on main water line from CLWS
Safety Measures … • each construction worker will be registered to be on site, wear a hard hat with a registration sticker, and a colored site specific vest • construction workers will be subject to background checks • school community and construction workers will be segregated