An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. North Central Region Construction Conference March 7, 2013

  2. Overview • Utility unit staff • Utility unit can help • Wisconsin Statute 182.0175 • Conflict or Means and Methods • Compensable utility relocations • Non-compensable utility relocations • Process • Documentation

  3. Utility Unit StaffWis. Rapids Office • Mike Maurer • 715-421-8059 • michael.maurer@dot.wi.gov • Richard Rogers • 715-421-8078 • richard.rogers@dot.wi.gov • Bryan Magnuson (DTSD Consultant) • 920-609-3703 • bryan.magnuson@dot.wi.gov

  4. Utility Unit StaffRhinelander Office • Terry Catlin • 715-365-5763 • terry.catlin@dot.wi.gov • Josh Gerrits (DTSD Consultant) • 715-846-8401 • josh.gerrits@dot.wi.gov • Steve Kienitz • 715-365-5762 • stephen.kienitz@dot.wi.gov

  5. Utility Unit StaffPermitting • Terry Catlin (Rhinelander) • 715-365-5763 • terry.catlin@dot.wi.gov • Keith Rutkowski (Wis. Rapids) • 715-421-8035 • keith.rutkowski@dot.wi.gov

  6. Utility Unit StaffWis. Rapids and Rhinelander • Mike Baumann (Utility Engineer) • 715-421-7393 • michael.baumann@dot.wi.gov • Jordan Kelbley (Utility Supervisor) • 715-421-8041 • jordan.kelbley@dot.wi.gov

  7. Utility Unit Can Help • Navigating laws • Conflict resolution • Conflict or Means and Methods • Compensable or Non-Compensable • Assist determining compensability • Coordinate approvals • Create documents • Process • Documentation

  8. Wisconsin Statute 182.0175 • The contractor must expose (pot-hole) the underground utility facility at reasonable intervals • Note: The utility company is not responsible to expose underground utility facilities

  9. Conflict or Means and Methods • Underground facility with 18 inches of excavation limits • Overhead facility too close to crane • Above ground facility with two feet of face of curb • Underground facility cannot withstand weight of equipment • Soil not stable so underground facility requires protection

  10. Conflict or Means and Methods • How was contractor anticipated to build project? • What equipment was contractor anticipated to use? • Specific equipment required to avoid utility conflict? • Are plans and special provisions consistent? • Contractor follow plan or did changes occur? • Issue based upon law/engineering or convenience?

  11. Example Conflict or Contractor’s Means and Methods • Plan calls for non-integral curb and gutter • Contractor chooses to do integral curb and gutter • Utility facilities two feet or more from face of curb • No conflict so contractor responsible for all costs associated with adjusting utility facilities or working around them

  12. Example Conflict or Contractor’s Means and Methods • Work Plans approved with overhead wires over a bridge deck • Special provisions and plan developed with the overhead wires over the bridge deck • Bridge can be built with 10 feet of clearance between adequate equipment and overhead wires • No conflict so contractor responsible for all costs associated with adjusting utility facilities or working around them

  13. Compensable Utility Relocations • Utility has a land right • Easement • Prescriptive rights • Previous Conveyance of Rights document • Other • Second Move • State Statue 84.295 (4m)

  14. Non-Compensable Utility Relocations • In right-of-way by permit • Have not relocated • Second Move due to utility company error • Construction Permit

  15. Process • Who has authority • Compensable • Non-Compensable • Who to inform • Utility company • Project manager • Utility engineer/coordinator

  16. Documentation • Diary entries • Who, what, where, when • Utilities marked • Potholing locations and utility elevations • Controlling item affected • Delay or inconvenience • Other information as needed • Pictures • Make sure has some scale to it • Make sure get whole area • Documentation reports • Project Manager/Leader • Utility Company

  17. Project Manager/Leader Documentation Report

  18. Utility Company Documentation Report

  19. Questions or Comments? • Mike Baumann • 715-421-7393 • michael.baumann@dot.wi.gov