An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Safety and Mission Assurance Monthly Status Report (MSR) December 2012 Jorg Fischer, PFP MAM

  2. SMA SUMMARY • Supported the monthly ESD Control survey – no issues • Supported the monthly calibration checks – no issues • Provided cleanroom support: cleaning of parts, supply, and maintenance, for all MAVEN cleanrooms • Alert responses: Updated the alert response database - no impact reports for all December alert items. • Continuous inspections of Flight assembly and test areas Provided support for delivery of the instruments to LM • Provided support for S/C integration at LM • Polymerics: Mix record database, updated. Performed polymeric witness sample testing, filing, inspections, and close-out. • Performed FLT document reviews, and updates for the EIDP

  3. SMA SUMMARY • Supported the delivery of Flight Instrument to Lockheed Martin, CO and S/C integration activities of the Instruments • Cleanroom Training at LMCO • Instrument unpacking and set up for post ship CPT’s • Instrument Installation oversight • Harnessing of instruments • General technical and QA support at LMCO • Support of SWEA – Tuning efforts, repair/rework, and testing of the SWEA instrument. • SWEA HV Board – Post Anomaly Inspections • SWEA PreAmp Board – Removed and Replaced all Preamps • Assembly and Disassembly Technical activities and Inspection

  4. PFR Detail • Updated PFR/NCR/LL data base • PFR status report list sent to GSFC - weekly • Provided assistance to SSL engineers with PFR form and related item close-out documentation PFR Status (12/27/12): • Problem count 132 • MRB problems: 87 • NCR problems: 40 • Closed: 120, Open: 5, VOID:5 • Monitor: 3 (SWEA PFR 059, 115, 122) • Open Problems: 3 MAVEN_PFR _128_STATIC_RTD_Thermo-couple_test MAVEN_PFR_130_NCR_SWEA_TVAC_Test MAVEN_PFR_131_SWEA_TVAC_Power_Supply_Instability

  5. SMA Other activities include the normal, ongoing participation in instrument and FRB/MRB meetings, discussions, reviews and comments. SSL SMA provided continued operator training and re-certification services, stockroom, shipping, chemical inventory, ESD control, and safety checks.

  6. SMA SUMMARY – Concerns • All PRFs are worked to close and will be addressed at a MRB/FRB closure meeting at the beginning of January • All concerns are well understood and are closely monitored by SSL and GSFC QA. • Pending – SWEA

More Related