1 / 39

Particles and Fields Package Monthly Status Review (MSR) May 20, 2010

Particles and Fields Package Monthly Status Review (MSR) May 20, 2010. Dave Curtis, PFP PM. SSL Contracting Status. Phase RR contract mod funding running out. Phase B/C/D Contract negotiations in progress Delivered IT Security, H&S, OCI plans Developed plan to deal with IT Security clause.

nanji
Télécharger la présentation

Particles and Fields Package Monthly Status Review (MSR) May 20, 2010

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Particles and Fields Package Monthly Status Review (MSR) May 20, 2010 Dave Curtis, PFP PM

  2. SSL Contracting Status Phase RR contract mod funding running out. Phase B/C/D Contract negotiations in progress Delivered IT Security, H&S, OCI plans Developed plan to deal with IT Security clause

  3. Schedule Status Designs ready for PDR All pre-PDR design work complete Long lead procurements in progress Peer Reviews in progress All complete except MAG Working to complete pre-PDR deliverable documents Next slide

  4. Pre-PDR CDRLs CDRLs FSW-01, SDP, Final @ IPDR-30 MA-01, MAIP, Final, IPDR-30 SE-04, Fault Protection Design, @PDR SE-09, Instrument Specifications, Preliminary, @IPDR SE-16, Verification Plan [preliminary] @ PDR SE-17, Gold Rule Compliance, @IPDR IT-01, I&T Plan, Prelim @ IPDR IT-06, Environmental Test Plan, prelim, IPDR-10d PM-14, IPDR Package, IPDR-10d MAIP CDRLs (Rev C) 3-2, Prelim. Safety Requirements Compliance Checklist @IPDR Checklist from Project promised 3-5, Prelim. Safety Assessment Report, @ IPDR Questionnaire from Project promised 4-1, Reliability Program Plan (Part of MAIP: Final @IPDR) 4-3, Prelim. FMEA, CIL, @IPDR 4-9, Prelim. Limited Life List, @IPDR 11-2, Prelim. Mat & Proc List, @IPDR 11-10 Prelim. Life Test Plan for Lubricated Mechanisms 12-3, Prelim. Parts Identification List, @IPDR

  5. Manpower • Ramping up nearly complete • Closing in on final new hire • SWIA/STATIC additional ME support (interviewing) • QA team is still short • Ron Jackson will not be returning • Looking at hiring a subcontractor to help with parts • Also working on opening a new position

  6. Accomplishments Completed review of pre-PDR ICD & MICD Completed Software Requirements Review Completed all pre-PDR peer reviews except MAG next week Completed and submitted MAIP, Fault Mode Description Document, FMEA, Limited Life List, Gold Rules Compliance Matrix, Software Requirements to MIS Held a PCB to work on SSL PIL Long lead parts identified, in work @ GSFC Completed development of SSL MAVEN Electronics Lab More in instrument sections…

  7. Ongoing Work Supporting Project planning process Supporting EMC, Payload, SDT working groups Working parts issues with PCB Working off peer review actions Preparing for iPDR Working on pre-PDR deliverables Purchasing long lead parts

  8. Trades Considering changing LPW boom whip caging Nick Jedrich Mechanical Peer Review recommendation Change from caged to fixed whip Deletes caging mechanism mass & resources Deletes whip hinge Deletes an actuation Simplifies qualification Concerns being investigated Enhanced vibration on whip, preamp Have ideas for mitigations which look promissing Potential damage to exposed whips during I&T Possibly remove whip for some of ATLO SSL & LM current see no show-stoppers

  9. Issues [1] Magnetics Current sensor location on solar array probably does not work Too close to solar array strings AC magnetics too high Working with Project on alternatives

  10. Issues [2] SWEA Surface Treatment Need to modify thermal characteristics of surfaces in SWEA aperture to avoid excessive heating - candidate solutions in work Candidate solutions need to be evaluated for Atomic Oxygen effects, charging effects, thermal properties, and robustness AO test being organized Current candidates: DAG213, Ebanol-C, Black Nickel SWIA and STATIC also interested SEP detector Atomic Oxygen effects Heritage instruments survives AO, but we would like to test a MAVEN detector if possible. Will be part of planned test

  11. Issues [3] Amptek HV801 failures Seems to be a lot workmanship issue New lot in work at Amptek, but not certain they will be better Projects ahead of MAVEN in trouble, will have higher priority for parts SWIA, STATIC use HV801 Alternative VMI part has acceptable performance Tested in breadboard Much too large for existing layout Significant changes would need to be made to accommodate mass, schedule impact VMI might be convinced to make a smaller part GSFC parts working on this SSL might be able to make an equivalent part

  12. Issues [4] SWEA Planetary Protection CESR part of SWEA FM build in progress Will be assembled before the breakup/burnup analysis complete Current PP plan indicates SWEA is likely to burn up SWEA is small, not a large contributor even if it does not burn up Looking into how clean SWEA fabrication will be Much of CESR SWEA has stringent contamination concerns due to MCP, and so is already built in very clean conditions CESR Electronics assembly is TBD – waiting on a response from CESR Need to decide if we need extra steps such as bio assay

  13. Issues [5] Launch Loads The current random vibe levels in the ERD are significantly higher than anything we have worked to on previous missions 23GRMS for forward deck mounted instruments 47GRMS for MAG MAC curve limit loads are as high as 72g Corresponds to design loads significantly greater than 100G, which is the usual design target at SSL Greater than qualification level for heritage instruments which were expected to fly with minimal changes SWEA, SEP, LPW booms A concern for some structures Historically loads come down significantly once we get CLA CLA is still months off, but well before CDR PFP plan is to follow LM’s lead and not design to these unrealistic loads When CLA comes in there is a risk we will have to do some redesign

  14. Top Risks • New risks 14,15,16

  15. Risks List [1]

  16. Risks List [2]

  17. PFP Mass EUV NTE mass increase [CCR164, approved] Other small changes to CBE

  18. Mass Tracking Chart

  19. PFP Power Include CCR157 Need to reallocate NTE amongst instruments to level magin Liens: Expect to need operational heat during eclipse None allocated for most instruments; amount needed pending thermal analysis Preliminary estimates included for MAG and EUV

  20. PFP Power Trend

  21. PFP Data Rate Per 2009-6-9 allocations from Bruce

  22. MAVEN Magnetometer Status May 19, 2010 Connerney, Sheppard, Schnurr, etc.

  23. GSFC/MAG - Accomplishments Last Month MAG instrument definition now mature. Finalized Peer Review plans – May 25 1:00 pm GSFC 34. Steve Battel, Ken Wagner, Dave Sohl (Curtis, Jedrich, etc.) Provided preliminary sensor assembly and attachment bracket mechanical drawings to UCB/SSL/LM. Assumes sensor accommodated on outer edge of SA substrate panel (1” thick M55J Aluminum honeycomb/CC facesheet panel) Dave Sheppard and Jim Odom met in Denver to discuss the MAG MICD with LM staff (5/10-11/2010). Supported continuing Spacecraft Magnetics Control Board discussions.

  24. Near Term Plans & Open Issues MAG Peer Review preparation. May 25 date selected for tabletop peer review Draft SIP. PDR Preparation. MAG Sensor accommodation options under discussion. Extend the SA panel substrate (1.5 m from SA strings may be possible). Addition of a third hinged panel (may provide ~2 m extension). Other boom proposals (STEREO-like, Astromast-type extensible boom, etc.) mentioned in this context.

  25. MAVEN PFP SWIA Status May 2010 Jasper Halekas, SWIA Lead

  26. SWIA Progress • MICD complete and reviewed • No major issues • Mechanical design presented at peer reviews • A few concerns on purge and attenuator mechanism • Analyzer and front end design presented at peer reviews • No major issues • Preamp and Anode schematics presented at peer reviews • No major issues • Digital schematics and FPGA design presented at peer reviews • Numerous useful suggestions for increasing stability and reducing noise • MCP specifications complete • High current plates approved by project • Quoting in progress with Photonis

  27. SWIA Issues • Staffing • Mechanical engineer staffing continues to be an issue • Greg Dalton becoming overloaded with STATIC, SWIA, and RBSP responsibilities • New ME hire in progress • High launch loads • Extremely high launch load requirements driving mechanical design • Without relief, these could require overdesigning and many changes to heritage designs • Looking at mitigation for HV801 failures

  28. MAVEN PFP STATIC Status May 2010 Jim McFadden, STATIC Lead

  29. STATIC Accomplishments Documentation prepared for pre-PDR reviews STATIC pre-PDR Peer reviews completed Inputs to Flight Software specification completed Carbon foil mounting fixtures designed VMI 15 kV multiplier prototype delivered Modifications to 15 kV HV connector design discussed along with assembly procedures for assembly of parts together Modifications to prototype Anode and Preamp board provided to tech for layout changes for engineering model boards. Test pulse generator for preamp-TDC-Digital testing delivered. Met with representatives from Photonis to discuss MCP order.

  30. STATIC Open Issues RFAs being collected from pre-PDR Peer Review Investigating modification to deflector design to eliminate or reduce scattered ions gaining access into the sensor Stability of the STATIC HV Sweep – testing still on hold due to RBSP conflicts with EE. Waiting on feedback from McBride on TDC part changes. STATIC FPGA still in development – need new test setup for complete throughput test (anode-preamp-TDC-Digital). Mechanical Attenuator still in development – handed off from Bill Elliott to Greg Dalton. Waiting on feedback from building maintenance with regard to changes in clean room (320) ventilation. New 15 kV / MCP board layout to proceed when EE is available.

  31. MAVEN PFP SEP Status May 2010 Davin Larson, SEP Lead

  32. SEP Accomplishments Went through Peer Review successfully with only minor RFA’s. Settled on MAX9202 comparator for baseline circuit design. Shaping circuit poles/zeros (resistor – caps) finalized. Getting thin foil quotes from Luxel.

  33. SEP Open issues FPGA SPEC sheet needs another internal review. (I don’t trust Peer review completely) Board layout. RFA’s to be answered from peer review

  34. MAVEN PFP PFDPU (and GSE Hardware) Status May 2010 Dorothy Gordon, Tim Quinn

  35. DCB Status PFDPU Processor DCB Schematics in process (about 90% complete) Presented at Peer Review Latest Power and Area estimates: FPGA Daughter Card FLASH Daughter card schematic generated RTAX Daughter card schematic pending Open Issues regarding daughter card strategy Signal termination strategy Insertion/Removal Plan Thermal Relief

  36. DCB PCB Preliminary Placement

  37. PFDPU Peer Review Digital/FPGA Peer Review held on May 10, 2010 Next Steps & Open Issues Continue with DCB and FPGA Daughter Card Schematics Open Issues Peer Review Action items Addition of analog mux to DCB Board FPGA Daughter card implementation details

  38. GSE Status GSE (MISG: MAVEN Instrument/IDPU Simulator GSE) The MISG PCB boards have been received All parts for the first board are in house Next Steps Parts kitting and loading of MISG #1 MISG FPGA development

  39. GSE Software Status GSE application development work continues IOG (Instrument Operations GSE) telemetry and command control system (GSEOS) evolution continues using STATIC Prototype Board Parsing and displaying full complement of STATIC telemetry packets in raw form, while saving packet types to file Commanding instrument successfully Test network topology set up and running: Includes router, IOG running GSEOS, and GPIB interface with power supply IOG controlling power supply via GPIB interface SSG software development begun – will control SSG hardware interface

More Related