An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Central Engineering Design (Electrical) Engineering Process Bertina Chan Weina Lin Hsiao-Yun Lu Sankarbharathy Ponnusamy Susu Wang

  2. Overview • Company Overview • Design Engineering • Design Engineering Process (DEP) • Problems with Current Process • Recommendations • Conclusion

  3. Company Overview • One of the largest investor-owned, energy-delivery companies in US • Annual revenue of $13 billion and total assets of $34 billion approximately • It owns and operates the world’s largest district steam system • Provides electricity and gas as well

  4. Design Engineering • Consists of Electrical Design, Mechanical Concept/3D Design, & Transmission/Civil Design • Ensures safe, reliable design operation and maintenance of the system • Provides design schematics of all Company electric, gas, and steam generating plants, electrical substations, and transmission and commercial facilities

  5. Design Engineering Process(Electrical) • Scope &Budget Oversee &Upgrade Project Scope of Work Works on the project • Match • Not match • Match • Not match Top management Engineering Department Engineer Electrical Design Scope review Final package Review & comments Upgrade & Construct Drawing layouts As-built Review &Field walk Agreement As-built

  6. Problems with Current Process • Miscommunications • Schematics (Drawings) vs. Real Field Conditions • Human Resources – Age Gap within the Designers

  7. Cause & Effect Diagram • Identify the possible root causes, the basic reasons for a specific effect, problem or condition • Helps determine root causes • Increases process knowledge • Identifies areas for collecting data • Analyze existing problem

  8. Cause & Effect Layout CAUSE EFFECT Miscommunication Age gap Lag in project time Bad field conditions

  9. Recommendations • Miscommunication • Project Checkpoints strategically placed within certain stages of the DEP. • Schematics vs. Real Field Conditions • A full-time Designer at the station to upgrade existing drawings to current field conditions • Current Designers assigned to on-going projects will update drawings during construction

  10. Recommendations (cont’d) • Human Resources – Age Gap • Hire retirees to give seminars/classes to incoming and present employees • Pair experienced designers with inexperienced designers

  11. Conclusion If the necessary changes are implemented: • Detailed training guide for new employees • Duration of DEP would be decreased and run smoother. • Department would spend less than $8 million on outside services