An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Capacity Building Programme on the Economics of Climate Change Adaptation Supporting National/Sub-National Adaptation Planning and Action NORTH LUZON IRRIGATION PROJECT: Philippine Country Report 2nd Regional Training Workshop The Grand Milleninum Sukhumvit Hotel, Bangkok, Thailand 30 September – 4 October 2013

  2. Project Profile • The NLIP generally intends to reduce the adverse effect of climate change and support enhanced water management in rural areas through the construction of water impounding facilities. • Specific objectives: • Provide sustainable development in the rural areas by improving agricultural productivity; • Increase agricultural production through the provision and improvement of irrigation and drainage infrastructure in the project area; and • Increase farmers’ income. Outline of the Presentation • Background • Project Component and Interventions • Cost and Benefit 2nd Regional Training on ECCA 01 October 2013 2

  3. Project Profile • Location: • Isabela Province, Cagayan Valley • Beneficiaries: • 685 to 933 families in five (5) • barangays • Implementing Agency: • National Government • Implementation Period: • Four (4) Years • Project Cost: • US$ 9.53 Million Outline of the Presentation • Background • Project Component and Interventions • Cost and Benefit 2nd Regional Training on ECCA 01 October 2013 3

  4. Project Profile • Involves 4-year construction of: • 34-meter high earth-filled dam across the Pasa river • Reservoir with an active storage of 4.28 mcm • 5.93 km main canal • 16.20 km lateral canals • Irrigates 980 has Outline of the Presentation • Background • Project Component and Interventions • Cost and Benefit 2nd Regional Training on ECCA 01 October 2013 3

  5. Project Components Outline of the Presentation • Background • Project Component and Interventions • Cost and Benefit 2nd Regional Training on ECCA 01 October 2013 4

  6. Costs and Benefits Environmental Costs 2nd Regional Training on ECCA 01 October 2013 5

  7. Outline of the Presentation • Background • Project Component and Interventions • Cost and Benefit Thank you! Salamat! 2nd Regional Training on ECCA 01 October 2013 6