The East-West Interconnector Access Rules, established on March 11, 2011, outline critical project milestones and compliance with congestion management guidelines. Key milestones include government approval in March 2009, planning permissions secured by September 2009, and commencement of cable works in Wales and Ireland between 2009 and 2010. The access rules facilitate explicit and implicit auctions through a unified auction management platform for both EWIC and Moyle, ensuring a scalable solution for potential future interconnectors. Regulatory approval is expected by May 31, 2011.
E N D
East West Interconnector Access Rules 11th March 2011
Recent Project Milestones • Government Approval / Contract Award Mar 2009 • Planning Permission in Britain & Ireland Sep 2009 • Commencement of Cable Works in Wales Nov 2009 • Funding Secured/FNTP Mar 2010 • Commencement of Cable Works In Ireland Jun 2010 • Granted Foreshore Licence in Ireland Dec 2010 • Converter Station Sites Construction Feb 2011 • Marine Installation Works Phase 1 Q2 2011
Access Rules - key features Will be fully compliant with the Congestion Management Guidelines Coordinated with other regional interconnections to ensure harmonised approach Access Rules will apply to East-West Interconnector. A different (but coordinated) set of access arrangements will apply to Moyle Access Rules will cover: Explicit Auctions → Auction Management Platform (AMP) Implicit Auctions → Single Electricity Market (SEM)
Auction Management Platform - key features Single Auction Platform for both EWIC & Moyle Different access rules and auction products for EWIC & Moyle Solution scalable to accommodate additional interconnectors as required Uses same service provider as IFA & BritNed (i.e. Unicorn) Interfaces to EirGrid, SONI, and NGC System Operators, Interconnector Owners, and EirGrid and SONI Interconnector Controllers, SEM, BETTA
Consultation timeline for East West Access Rules Regulatory Approval ? End of Review 31 May ‘11 End date 18 Mar ‘11 Start date 18 Feb ‘11 Submit for approval 15 Apr ‘11