Offshore Projects in China Advantages & Risks

Offshore Projects in China Advantages & Risks. Sam Shen, COOEC April, 2012. CONTENTS. Offshore Projects. China Advantages. Risk Control Method. Going into More Difficult Environment. … …. 160 FPSOs in the worldwide in 2010. 40-50 FPSO facilities are needed in the next 5 years.

lilah
Télécharger la présentation

Offshore Projects in China Advantages & Risks

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Offshore Projects in ChinaAdvantages & Risks Sam Shen, COOEC April, 2012

  2. CONTENTS Offshore Projects China Advantages Risk Control Method

  3. Going into More Difficult Environment …… 160 FPSOs in the worldwide in 2010. 40-50 FPSO facilities are needed in the next 5 years. Oil has been produced from offshore locations since the late 1940s. The first oil FPSO was the Shell Castellon, built in Spain in 1977 The first oil FPSO fabricated in China named “Bo Hai You Yi” was operatered in 1993. Shell and Samsung announced an agreement to build up to 10 LNG FPSOs in 2009 1940s 1970s 1990s 2000s Present … Fixed Platforms + Jackets → Floating Facilities + Subsea Units From shallow to deep, remote, even Arctic Areas

  4. Increasing Demand for Energy Facilities FPSO Demand Billion • More demand for deep water facilities especially in South Americas and Western Africa • Many large-scale Onshore LNG Projects

  5. Projects / Modules Getting Bigger • BZ34-1 Project (CEP/ 9,200T) • Jack-up Drilling Rig (6800T×4) • LD 27-2/32-2 Project (PSP/11,500T) • Nickel Modularized Plant (40,000T) • JX 1-1 Project (CEPA/ 9,900T) • JZ25-1SProject (CEPA/ 9,800T) Page 5

  6. Modularization Trend Fabrication in Yards Offshore Transportation Site Installation

  7. What is required? • Innovative and Reliable engineering support • Large & first-class Fabrication Facilities • A large pool of experienced workers in particular • Availability of necessary materials / equipment locally • Sound logistic support like heavy lift / sea transportation

  8. CONTENTS Offshore Projects China Advantages Risk Control Methods

  9. Advantages of Yards in China • Most Material and equipment available in China • Technical Compliance of Chinese Materials • Cost and time effectiveness of Materials made in China • Adequate Skilled Workforce Available • Many Excellent Yards already Qualified by International Clients

  10. COOEC Qingdao Yard Facilities • Quay Line: 1,645 M • Quay Water Depth: 10~12.4 M • Total Area: 1,200,000 M2 • Annual Fabrication Capacity: 270,000 T • Dry Dock: 420 M ×110 M ×13.9 M The yard has experience with EPCI contract in the Asia Pacific region for oil & gas industry.

  11. International Projects Reference • Duration: 2007.09-2008.03 • Description: 3 Topside Modules • Weight: 700 T • Client: MODEC Opportunity Topsides Pyrenees FPSO Project PB GAS II • Duration: 2007.09-2008.06 • Description:10 Topside Modules • Module Weight:6,900 T • Client:MODEC • Duration: 2008.04-2009.08 • Description : 11 Topsides Modules • Module Weight: 6,445 T • Client: Petrobras • Duration: 2008.04-2009.09 • Description: 10 Topside Modules • Module Weight: 5,500 T • Client: BHP Billiton Page 11

  12. Modular Plant for Xstrata COOEC strategically extended business to onshore market by signing a construction contract in 2008, which is an integrated and modularized nickel metallurgical plant. • Client : Xstrata, Canada • Construction Yard : COOEC Qingdao Yard • Site Location : New Caledonia • Scope of Work : Shop Design, Procurement & Construction • Construction Weight : 30,000 Tons Page 12

  13. Gorgon Project for Chevron • Project Name : Chevron GORGON PARs • Duration : 2011.01-2012.09 • Description 157 Modules • Weight : 37000 T • Client: Chevron Page 13

  14. Qualified and Accepted by International Clients We Can Do It! Page 14

  15. Petrobras Opportunity FPSO Topsides Project TSJOC FPSO Topsides Project BHPB Pyrenees FPSO Topsides Project COOEC FPSO Experience HAIYANG SHIYOU 116 (Wen Chang Project) HAIYANG SHIYOU 115 (Xi Jiang Project) HAIYANG HIYOU 113 (BZ25-1Project) HAIYANG SHIYOU 112 (CFD Project) 15

  16. CONTENTS Offshore Projects China Advantages Risk Control Methods

  17. Risk Control Method • Choose the right vendor / yard – Pre-qualifications prior to order placement; • Sound Quality & HSE Management System • Equipment and Facilities • Personnel Qualifications • Project References CHINA

  18. Risk Control Method • More attention to process control for new partners; • Place more staff for supervision and surveillance • Training Programs (once found necessary) • Close Monitoring of Progress Performance • Minimize Culture conflict CHINA

  19. Risk Control Method • Establish Strategic Partnership with First Class vendors • Select Best Partners • Establish Cooperation Framework • Revise / Improve Cooperation Model CHINA

  20. THANK YOU! ADDRESS: No.1078, Dan Jiang Road, Tanggu, Tianjin, 300451, P.R.China CONTACT : Mr. Li XiaoWei TEL: +86 22 6690 8879 FAX: +86 22 6690 8899 WEBSITE: www.cnoocengineering.com E-MAIL: lxw@mail.cooec.com.cn ADDRESS: No.492, Lian Jiang Road, Qingdao Economic & Technical Development Zone, Qingdao, 266555, P.R.China CONTACT : Mr. Shen Weihe TEL: +86 532 8675 8188 FAX: +86 532 8675 8987 WEBSITE: www.cnoocengineering.com E-MAIL: mbteam@mail.cooec.com.cn swh@mail.cooec.com.cn