An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GLC Overview LCPAC 2004 (Feb. 20, 2004) Nobu Toge, KEK Accelerator Lab. GLC Overview (N.Toge) - LCPAC 2004

  2. GLC Schematic Layout GLC Overview (N.Toge) - LCPAC 2004

  3. Main Linac Unit GLC Overview (N.Toge) - LCPAC 2004

  4. Beam Structurevs RF Pulse GLC Overview (N.Toge) - LCPAC 2004

  5. X-band Global Parameters GLC Overview (N.Toge) - LCPAC 2004

  6. X-band IP Parameters GLC Overview (N.Toge) - LCPAC 2004

  7. Main Linac Parameters (1) GLC Overview (N.Toge) - LCPAC 2004

  8. Main Linac Parameters (2) GLC Overview (N.Toge) - LCPAC 2004

  9. Major development in 2003 • Efforts on R1 and R2 items as laid out in TRC-II report in collab. with the NLC team. • Part of R1, R2 items cleared – PPM basic validation, SLED-II power compression. • Some remain – Accelerator structures • Efforts to continue in 2004 – Acc. structures. “Fuller” demonstration of SLED-II with additional waveguides and structure loads downstream. • Numerous beam control technology R&D at ATF. • Progress made in low-intensity emittance studies (single- vs multi-bunchgive consistent results at low-intensity) • Steady progress in I&C hardware (e.g. laser wire detector, ODR, XSR) • Construction and operation of GLCTA. • A basic 2-klystron power source system was built (~ 60MW, 400ns). • Initial system commissioning has begun and is expected to continue in 2004. • Will plan extension of the system to include SLED-II pulse compression or other upgrades in ~2 yrs. GLC Overview (N.Toge) - LCPAC 2004

  10. Updated TRC-II Information • http://lcdev.kek.jp/TRCII/TRCupdates.html • Status update of R&D efforts related to R1/R2 items • http://www.slac.stanford.edu/xorg/ilc-trc/2002/2002/report/03rephome.htm • TRC-II main web site • http://www.ligo.caltech.edu/~donna/ITRP_Home.htm • ITRP web site GLC Overview (N.Toge) - LCPAC 2004

  11. Quick Dictionary • TRC-II (Technical Review Committee-II): Founded under ICFA in 2001. Charged to review the recent status of LC design schemes and R&D(SLAC-R-606, published in early 2003)。 • R1 : “R&D needed for feasibility demonstration of the machine” • R2 : “R&D needed to finalize design choices and ensure reliability of the machine” • R3 : “R&D needed before starting production of systems and components” • R4 : “R&D desirable for technical or cost optimization” • ILCSC (International LC Steering Committee): Founded under ICFA in late 2002 to act as a steering body for world-wide cooperation on LC development. • ITRP (International Technology Recommendation Panel ): Placed by ILCSC in early 2003 to recommend on “Technology Selection” for LC GLC Overview (N.Toge) - LCPAC 2004

  12. PPM Klystron Status • Specifications [TRC R2#2] : Simultaneous achievement of • 75MW, • 1.6ms, • 120 Hz , or higher • Results in 2003: • Two PPM tubes built by KEK are approaching the spec. goals above. • A PPM tube built by SLAC cleared the goal in Fall, 2003. GLC Overview (N.Toge) - LCPAC 2004

  13. SLAC XP3-3 A.Vlieks@ISG-11 GLC Overview (N.Toge) - LCPAC 2004

  14. PPM Klystrons R&D • PPM #4 : under testing at KEK • Achieved: • 75MW, 1.7ms, 50Hz • Status: • - Testing at KEK after window repair has been temporarily concluded as of this week. Y.H.Chin@ISG-11 Y.H.Chin@ISG-11 • PPM#2 : under testing at SLAC Klystron lab. Achieved: • 75MW, 1.7ms, 60Hz • 68MW, 1.7ms 120Hz • Status: • - Gun repair nearly completed. PPM #5 : after baking Status: - Readied for testing to start at KEK Y.H.Chin@ISG-11 GLC Overview (N.Toge) - LCPAC 2004

  15. Plans for PPM Klystrons in 2004 • Existing tubes • PPM#5 :Has been built in 2003. Test to start at KEK in ~ March. • PPM#2 : Repair under way • PPM#4 : Temporarily concluded testing in Feb. • Some combination of KEK and SLAC PPM klystrons: Long-term high-rep-rate testing with a 2-pack IGBT modulator at SLAC. • New tubes • Further improvements to the body cooling system and electron gun. • More details: see presentation by Y.H.Chin GLC Overview (N.Toge) - LCPAC 2004

  16. Accelerator Structure R&D  Cells T.Higo Test Accelerator Struc.  Most of 60cm-long struc’s tested in 2003 include HOM slots and manifolds as required for GLC/NLC. J.Wang@ISG-11 GLC Overview (N.Toge) - LCPAC 2004

  17. Accelerator Structure Summary • Specifications [TRC R1#1]: Simultaneous achievement of • 60cm-long • ENL = 65MV/m, 400ns pulse length. • BD rate 0.1 / 1 hr in 60Hz operation. • Results in 2003: • A few strucs cleared the BD goal with ENL = 60MV/m, 400ns. • BD rate with ENL = 65MV/m remains x 2 ~ 3 of the goal. • Struc-to-struc variation of performance needs to be resolved. Some are suspected due to known anomalies during manufacturing or vacuum baking. • Much reduced BD rate observed with “ramped” pulse shape, known to be used for beam-loading compensation (All other typical high-power tests are done with rectangular pulses). Field Time GLC Overview (N.Toge) - LCPAC 2004

  18. High-Power Testing in 2002-2003. • H60-series built and tested in 2002-2003. • BD rate found to be prop. to gradient. • “Acceptable” BD rate performance at 60MV/m. • Performance not YET acceptable at 65MV/m. With pulse “ramping” substantial improvement seen. • Struc-to-struc variation of permance needs to be resolved. Keep eyes on manufacturing / heat processing. • Must accelerate the data collection with a plural # of structures with identical design and build. C.Adolphsen, Jan.2004 GLC Overview (N.Toge) - LCPAC 2004

  19. Plans for Acc Structures in 2004 • Highest priority: Additional construction of H60VG4S17-type structures  Improve the statistical / systematic confidence in performance observations of the latest struc design. • At SLAC expect to exploit the 2-moded SLED-II power source, in addition to the existing NLCTA test stations for accelerated, parallel testing. • Later this year we may reconsider - • More improvements to the structure design, or • GLC/NLC overall parameter optimization (ENL : 65  60MV/m gives only minor impacts on the cost, no impacts on the luminosity) • In parallel, try to improve the domestic capabilities: • More purely-made-in-Japan structures. • Build up infrastructure at GLCTA. • More details: see presentation by Toshi Higo GLC Overview (N.Toge) - LCPAC 2004

  20. Pulse Compression (2-moded SLED-II) Summary • Specifications [TRC R1#2]:simultaneous achievement of producing X-band RF power of • 475MW, • 400ns • Results in 2003: • Test at SLAC produced 475MW, 400ns at 30Hz on 12/4/2003. Continual operation for 100 hrs. • Used solenoid-focussing type klystrons x 4 as power source. • Maximum: 580MW, 400ns. GLC Overview (N.Toge) - LCPAC 2004

  21. Tested in 2003 Used solenoid-type klystrons x 4 56MW GLC Overview (N.Toge) - LCPAC 2004

  22. Input and Output pulses with SLED-II GLC Overview (N.Toge) - LCPAC 2004

  23. Plans for SLED-II in 2004 • Distribution of the SLED-II power to accelerator structures • Phase 1: 4 structures in Spring, 2004. • Phase 2: 4 more struc (8 in total) in Summer/Fall, 2004. • At each phase, semi-long-term operation at 60Hz. • Integration with structure testing in ~ Summer. • Integration with PPM klystrons later as found possible. • KEK team will contribute • Hybrids (overheight models) to use as “power splitters” • Personnel to participate in test operation at SLAC • More details: see presentation by Y.H.Chin GLC Overview (N.Toge) - LCPAC 2004

  24. 2004 Expansion of SLED-II testing Switching to PPM tubes as found possible Phase 1 Phase 2addition 56MW Introduce newly-built acc strucs as found available GLC Overview (N.Toge) - LCPAC 2004

  25. SLED-II additions in 2004 D.Schultz @ISG-11 GLC Overview (N.Toge) - LCPAC 2004

  26. Set up next to ATF. Possible beam acceleration exercise in the future. 2 solenoid-focused klystrons, straight power combiner, feeding one acc struc, as starter. Initial set-up built in 2003. Aim at testing ~ 65MV/m in 60cm-long structures in 2004. Later implement PPM klystrons. SLED-II also. Considering GLCTA as a homeground for building up domestic infrastructure / human resources. Continue full collaboration at NLCTA concerning rapid validation of required X-band technologies. For more details: see presentation by H.Hayano and T.Higo. GLCTA H.Hayano@ISG-11 GLC Overview (N.Toge) - LCPAC 2004

  27. GLCTA Hardware as of 2003 H.Hayano@ISG-11 GLC Overview (N.Toge) - LCPAC 2004

  28. Plans for GLCTA in 2004 • Stable delivery of 60MW, 400ns power to one 60cm-long accelerator structure • Powered by a pair of solenoid-focussed klystrons. • Misc improvement program in WR90 waveguide system. • Possibility of introducing circular WG for power handling margins. • Establish an acc struc test station similar to NLCTA.. • Preparation of RF power compression HW • New, PFN-based “two-pack” modulator delivery expected in Feb. • Commission the two PPM-focussed klystrons delivered in 2003. • Misc design and prep work for the pulse compressor hardware • More details: see presentation by H. Hayano, T. Higo, Y.H.Chin GLC Overview (N.Toge) - LCPAC 2004

  29. Summary • System Validation R&D for X-band (Higo / Chin) • Acc Struc: Clarify the high-power performance at around 60 – 65 MV/m in 2004. • PPM Klystron: Successful operation done in 2003. Will continue long-term + high-rep rate operation exercises in 2004. • SLED-II: Successful production of 475MW, 400ns pulses done in 2003. Will implement a full set of waveguide systems and acc structures downstream; and conduct a long-term operation exercise in 2004. • ATF (Hayano) • Beam physics: • Consistent emittance results in low-intensity single-bunch vs multi-bunch operations in 2003. Need to check high-intensity performance in 2004.. • Performance when wigglers are turned on. Study scheduled in 2004. • Beam instrumentation: Progress seen in understanding of laser-wire “thickness”, ODR, OTR, XSR. Continue efforts in 2004. • FEATHER: Fast beam feedback control exercise with nm-resolution BPMs. Prep efforts initiated in 2003, to continue in 2004. • Also in Japan • Modulator: Test operation of IGBT-type model scheduled in Spring-Summer, 2004 (Chin). • GLCTA: (Higo, Hayano) • Built in 2003. Will set up the system so that high-power operation of one 60cm-long acc struc becomes a routine in 2004. • Towards 2005, prepare implementation of SLED-II, with PPM tubes. • C-band (H.Matsumoto) • High-power test of acc struc: Scheduled at SPring-8 in spring, plus related development GLC Overview (N.Toge) - LCPAC 2004