Central Water Project Completion Act PL 102-575 “CUPCA”Program H. Lee Wimmer, P.E. CUPCA Program Manager April 23, 2014
CUPCA – FIVE MAJOR AREAS • Provo River / Utah Lake Special Studies • Water Management / Water Conservation • Diamond Fork System • Uinta Basin Replacement Project • Utah Lake System
WORK BREAKDOWN STRUCTURE • Level One (WBS 1) TOTAL PROGRAM • Level Two (WBS 2) SYSTEMS • Level Three (WBS 3) ELEMENTS • Level Four (WBS 4) PROJECTS • Level Five (WBS 5) SUB-PROJECTS
ORGANIZATIONAL BREAKDOWN STRUCTURE • Level One (OBS 1) WORKTYPE • Level Two (OBS 2) RESPONSIBILITY • Level Three (OBS 3) SECTION OF BILL • Level Four (OBS 4) PROJECTS
MASTER PROGRAM SCHEDULE • Organized by WBS • Milestones from PL 102-575 • Baseline FY1992 – FY2021 • Dependent on Federal Funding Received • Dependent on Local Funding Availability
SF Canyon Pipe SF – Provo Reservoir Canal Pipeline Milestone SF – Santaquin Pipeline DF Power 2010 2011 2012 2014 2015 2016 2017 2018 2019 2020 2021 Master Program Schedule • Based on projected receipt of federal funds
FINANCIAL TRACKING • Yearly Budgets by Tasks and Worktypes • Phased Workplan with Discrete Task Order Authorization • Progress vs Budget Tracked Monthly, Quarterly, and Annually • Monthly Financial Reports to Management Team, General Manager, and Board
Financial Summary – Dec. 31, 2013 • $814 million expended • $569 million federal • $245 million local • “Federal Advance” = $30,017,995 • July 1, 2014 – June 30, 2014 budget is $30,230,000 • Future annual budgets - $20 million/yr (+/-)
CUPCAProgram H. Lee Wimmer, P.E. CUPCA Program Manager April 23, 2014