Gain insights into Vermont's state decommissioning activities related to Vermont Yankee nuclear plant presented in April & May 2015. The activities range from public concerns addressed to emergency response drills and construction updates. Stay informed with ongoing regulatory filings and ANR efforts to ensure safe decommissioning.

marker
Télécharger la présentation

Overview of State Decommissioning Activities April & May 2015

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overview of State Decommissioning Activities April & May 2015 (Mostly from a VT Public Service Department Perspective) Presented by Tony Leshinskie, VT State Nuclear Engineer May 28, 2015 NDCAP Meeting

  2. PSD Role in VT Yankee Decommissioning • Assure Public concerns are voiced • Assure clear, current decommissioning information is available to State Agencies, NDCAP & Public • Support of NDCAP • Assure decommissioning activities benefit the People of Vermont

  3. On-Going PSD Filings • Oppose reduction of the Emergency Planning Zone (EPZ) to the VY Site fence line • Question several proposed uses of VY Decommissioning Trust Fund • Appeal discontinuation Emergency Response Data System (ERDS) feed used by the State Radiological Emergency Response Plan “It ain’t over ‘til it’s over!”

  4. Related to PSD Filings • Agencies to file comments on NRC’s Draft Environmental Assessment / Finding of No Significant Impact (FONSI) for VY EPZ Exemption Request (due 11:59:59 PM on June 1) • Upcoming Agencies-NRC Teleconference on Decommissioning Trust Fund Questions (currently scheduled for May 29)

  5. Emergency Preparedness Activities • Full State participation in 2 Hostile Action Exercises at VT Yankee • April 22 preparatory drill • May 13 FEMA-Graded Exercise • Test of State Radiological Emergency Response Plan and Offsite Response Organizations’ capabilities • Overall positive feedback from FEMA so far • Final report expected in roughly 1 month (~June 29)

  6. Construction of Second Spent Fuel Dry Cask Storage Pad at VY Site Certificate of Public Good Proceedings will be discussed in detail later this evening; However: • Public Service Board Status Hearing held on April 28, CPG Schedule subsequently ordered • Entergy supplemental, pre-filed testimony submitted on May 11 • PSD & ANR completed First Round of Discovery (questions on Entergy testimony) on May 27 • PSB Site Visit & Public Hearing (at Vernon Elementary School) on June 4 • Motions to Intervene Deadline is June 11

  7. ANR Efforts • Requested additional information and records on May 14, 2015 in an effort to fully understand what decommissioning activities were performed and whether any non-radiological issues were encountered during this work. This request was necessary as ENVY’s response to our original March 6, 2015 information request was insufficient and incomplete. • Conducted facility inspection on May 18, 2015. Investigated areas where building demolition occurred and reviewed waste disposal records. • Inspection identified some areas of concerns. ANR will request that ENVY conduct additional follow-up work.

  8. NDCAP Support NDCAP’s Annual Report for 2014 was submitted to the Governor’s Office and Legislature’s Committees on Natural Resources & Energy on May 7. • Incorporates final modifications approved at the March 26 meeting • One figure from Site Assessment Study added to summarize both radiological & non-radiological contamination on VY-site (text discussed radiological, but non-rad figure provided) • Side note: Duration of CBI / Catherine Morris contract extended through end of 2016 (opportunity to use existing funding)

  9. NDCAP Support Pursue potential site tours NDCAP edification: • Tour of Connecticut Yankee Spent Fuel Storage Facility, potential dates of June 25 or June 26 • Tour of Millstone-1 (a decommissioning BWR currently in SAFSTOR) • Facility is unable to honor request due to station’s busy calendar for the foreseeable future • Inquiring whether late autumn or 2016 tour dates possible

  10. State State Decommissioning Activities • Lastly note that the answers to many NDCAP meeting-related questions can be found at: http://publicservice.vermont.gov/topics/electric/nuclear • Any Additional Comments from PSD, ANR or VDOH? • Questions?