1 / 6

SPS 200 MHz RF Upgrade

SPS 200 MHz RF Upgrade. Eric Montesinos LIU-SPS coordination meeting 25 th April 2014. Amplifiers. Drivers (SSA): MS completed : 17 companies selected IT completed : selected company under qualification FC March 2014 Finals (SSA or Tetrodes ): MS completed : 7 9 companies selected

maude
Télécharger la présentation

SPS 200 MHz RF Upgrade

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 25th April 2014

  2. Amplifiers Drivers (SSA): • MS completed : 17 companies selected • IT completed : selected company under qualification • FC March 2014 Finals (SSA or Tetrodes): • MS completed : 7 9 companies selected • TS to be send out May 2014 • FC November 2014 Combiners (3 dB above 100 kW) • In house • TTE fellow Transmission lines (coaxial, 345 mm outer) • During Winter shutdowns 2015-2016-2017 Tetrode vs Diacrode (still SSPA, Klystron, IOT) LIU SPS RF

  3. April 2014 amplifiers Schedule 2016 2014 2015 December CERN approval for Series Production (after LD tests) Drivers IT : Invitation to Tenders FC : CERN Finance Committee FAT : Factory Acceptance Tests CERN AT : CERN Acceptance Tests LD Tests : Long duration tests : Long Technical Stop, No beams August Pre-series CERN AT October IT sent March First Series FAT June Pre-series FAT December Last Series CERN AT March FC Order placed 2015 2016 2017 2018 2019 March CERN approval for Series Production (after Pre-series LD tests) Finals June Ready for operation September First Series FAT May IT sent December FC Order placed June Pre-series FAT LSS3 upgrade & connection of amplifiers March 2017 CERN full RF tests December 2014 Decision for technology September 2015 First RF tests LIU SPS RF

  4. April 2014 9 months cavities re-arrangement 4 months RF Power conditioning 5 months LLRF commissioning 2011 2012 2013 2015 2016 2017 2014 2018 2019 Studies Tendering Construction Installation LLRF Design and proto Commissioning Start up LLRF Tests LLRF Series New RF Power Amplifiers and LLRF Studies Coaxial Lines Cavities pickups vacuumCV, EL LSS3 Tunnel Integration HBW (kicker and Pickup) Spare sections New power couplers Studies Authorizations Construction BAF3 RF Building Services Startup LIU SPS RF

  5. LIU-SPS RF upgrade Working Group Members LIU SPS RF

More Related