Asynchronous Circuit Design Framework with JBits for Xilinx FPGAs

DESCRIPTION

This paper presents JBits, a Java API developed for configuring Xilinx FPGA bitstreams that allows complete design control including routing, CLB configuration, and run-time reconfiguration. It emphasizes asynchronous circuit advantages such as modularity, low power consumption, and adaptable performance. JBits facilitates low-level configuration calls and supports building tools built upon its framework. The framework also introduces concepts such as four-phase signaling and dual-rail communication, enabling efficient asynchronous design and reconfigurable logic implementation. Future work includes defect tolerance techniques and enhancements for asynchronous methodologies.

1 / 13

Download Presentation
Télécharger la présentation

Asynchronous Circuit Design Framework with JBits for Xilinx FPGAs

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Building Asynchronous Circuits With JBits Eric Keller eric.keller@xilinx.com FPL 2001 FPL2001

  2. JBits Background • A Java API to configure Xilinx FPGA bitstreams • Provides complete design control • Routing • CLB configuration • Supports run-time reconfiguration • Allows for tools to built upon it • Example low-level configuration call: jbits.set(row, col, S1F1.S1F1, S1F1.SINGLE_EAST0)

  3. FPGA The JBits Environment RTP Core Library JBits API User Code JRoute API Remote Hardware BoardScope Debugger TCP/IP XHWIF FPGA Hardware Device Simulator

  4. Asynchronous Advantages • Modularity • Low power • Average-case performance • No clock distribution • Adapt to environmental conditions

  5. Why use JBits? • Complete control over circuit • Have some fixed routes and others auto-routed • Can pre-route modules to meet any delay constraint • Use templates to add delay to a net • Clean HDL for dual-rail cores • Combine asynchronous design and RTR

  6. Null Convention Logic • Developed by Theseus, Inc. • Four-phase signaling, dual-rail communication • Delay Insensitive (almost) • Occurs in very few situations • Easily analyzable • M-of-N gates • Output goes high when M of the N inputs go high • Output goes low when all N inputs go low • Symbolized by M

  7. NCL Full Adder Stage A single dual-rail net * Red lines represent high state A_0 A_1 2 3 Sum_0 B_0 B_1 2 Cin_0 Sum_1 3 Cin_1 Cout_1 Cout_0 Values of dual-rail net • 2 of 3 gate takes up 1 Virtex LUT • 3 of 5 gate takes up 2 Virtex LUTs A_0 A_1 val red red n/a red black 0 black red 1 black black null

  8. NCL Register A_0 2 A_1 NCL CIRCUIT 2 B_0 2 B_1 2 Low requests NULL High requests DATA 2 from_next to_prev • Implement 4-phase signaling • Receive NULLRequest DATARec. DATAReq. NULL

  9. RTPCore Overview 4 inputA + 4 output inputB 4 cout cin Bus inputA = new Bus(“inputA”, this, DATA_WIDTH); Bus inputB = new Bus(“inputB”, this, DATA_WIDTH); Bus output = new Bus(“output”, this, DATA_WIDTH); Net cin = new Net(“carryIn”, this); Net cout = new Net(“carryOut”, this); Adder adder = new Adder(“adder”, inputA, inputB, cin, output, cout); addChild(adder, Place.LOWER_LEFT); adder.implement();

  10. RTPCore Modifications • No support for Dual-Rail Signals • Added DualRailBus and DualRailNet. • Cores to convert between dual and single rail. • JRoute support for dual rail signals DualRailBus inputA = new DualRailBus(“inputA”, this, DATA_WIDTH); DualRailBus inputB = new DualRailBus(“inputB”, this, DATA_WIDTH); DualRailBus output = new DualRailBus(“output”, this, DATA_WIDTH); DualRailNet cin = new DualRailNet(“carryIn”, this); DualRailNet cout = new DualRailNet(“carryOut”, this); NCLAdd adder = new NCLAdd(“add”, inputA, inputB, cin, output, cout); addChild(adder, Place.LOWER_LEFT); adder.implement();

  11. Dual-Rail Full Adder DualRailBus inputA + 4 4 DualRailBus output DualRailBus inputB 4 DualRailNet cout DualRailNet cin DualRailNet Net inputA[0] inputA[1] 4 bit DualRailBus inputA[2] inputA[3]

  12. Delay Analysis - NCL Full Adder 4 inputA + output 4 inputB 4 • Average case performance • Depends on carry propagation • 0+0 no carry  lowest delay • 15+1 carry at each stage  longest delay

  13. Future Work • Defect Tolerance • Work around a defect on an FPGA • No timing analysis because of delay insensitive • Can place modules anywhere and they work • Other methodologies • Add support in JRoute for isochronic forks • symmetric and asymmetric • Examine FPGAs targeted to asynchronous design