Advancing Project Management Techniques by Matthew Forbes
Elevate last week's project management with Merlin Schedule, understanding critical paths, performance insights, and financial planning tips for successful project completion. Explore altering critical paths to meet real-time progress effectively.
Advancing Project Management Techniques by Matthew Forbes
E N D
Presentation Transcript
Do 1: Project Management By: Matthew Forbes
Purpose • Taking last weeks do 1 to the next level • Duration and completion • Planned expenses • To be able to know more systems, I used Merlin
Schedule explanation • ?- indicates this is an estimation and not net completed • Only A-C have been completed • The total duration is 65 days
Critical Path • The critical Path is • A-B-D-E-F-H • Before work started C was on the critical path in the place of A • A’s work took 4 weeks (not 2) • C’s work took 3 weeks (as expected)
Performance • Total expected duration is 17 weeks • 2 weeks behind schedule • A took 1 week longer than C • B took 1 week longer • Expected duration for activities D-H is 11 weeks
introspection • The critical path can be altered from the duration projection to what the actual completed time • It is important to use Project Management to keep track of any changes • This was the first time we also planned ahead with money