1 / 39

April 3, 2001 Washington, DC

2001 EMS Users Group. April 3, 2001 Washington, DC. PEPCO EMS Migration. Manley Higgins PEPCO Project Manager Mark Bruen KEMA Consulting Principal Consultant. EMS Migration. Migration Philosophy Overview of EMS Migration Phases Related Enhancement Efforts Future Phases

mills
Télécharger la présentation

April 3, 2001 Washington, DC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2001 EMS Users Group April 3, 2001 Washington, DC

  2. PEPCO EMS Migration Manley Higgins PEPCO Project Manager Mark Bruen KEMA Consulting Principal Consultant

  3. EMS Migration • Migration Philosophy • Overview of EMS • Migration Phases • Related Enhancement Efforts • Future Phases • Long Range Plan & Update Process • Challenges for the Future

  4. EMS Migration • Migration Philosophy

  5. Migration Philosophy • In 1995, PEPCO Adopted a Long-Term EMS Migration Philosophy to Keep the EMS “Ever-green”.

  6. Migration Philosophy • Migration Rationale: • Keep the system technologically current to meet the terms of the financial lease • To protect the investment in the operational procedures, EMS software, system design, & database. • To avoid obsolescence of hardware

  7. Migration Philosophy • Migration Rationale (cont.): • To support increased performance and capacity requirements • To allow for the addition and enhancement of system functions as business requirements change • Enhance the EMS to accommodate the implementation of large-scale Distribution Automation and Substation Automation projects

  8. Migration Philosophy • Migration Rationale (cont.) • And, to avoid the extreme and expensive effort of another EMS “forklift” replacement, including: • Procurement costs • System Testing • Cutover • Software Quality Control • Staff time commitment

  9. EMS Migration • Overview of the PEPCO EMS

  10. Overview of the Original PEPCO EMS • EMS is “Consolidated Control System” • Designed to support Transmission, Distribution, and Generation Operations • (Generation sold December 2000)

  11. Overview of the Original PEPCO EMS • Interfaces with other critical PEPCO and external systems including: • New Outage Management System • Corporate Systems • PJM

  12. Overview of the Original PEPCO EMS • Procured from ABB Network Management (formerly NMTI) • Delivered in 1993 • Initially commissioned in 1994

  13. Overview of the Original PEPCO EMS • Full featured EMS including: • SCADA • Graphical User Interface (not workstation based Full Graphics) • Distributed System w/ Proprietary Hardware Front-ends • Full Advanced Applications Suite • Real-time and Study • PEPCO Specific Applications

  14. Overview of the Original PEPCO EMS • Dispatcher Consoles • Transmission Dispatchers • Load Dispatchers • Transmission Shift Supervisors • Distribution Shift Supervisors • System Support Consoles • Development and Testing Facility • Dispatcher Training Simulator

  15. EMS Migration • PEPCO Migration Phases

  16. Migration Phases • PEPCO established a multi-year migration program: • To fully migrate the EMS every seven years. • PEPCO’s management committed to to fund the effort to avoid the high costs of another procurement.

  17. Migration Phases • Migration Phase I – 1995 – 1996 • Open Systems Platform Enhancements including: • Introduction of Dec Alpha Hardware Platform • Operating System Upgrades • VAX VMX to UNIX • Intel RMX to UNIX

  18. Migration Phases • Migration Phase I (cont.) • Conversion of Code to C • (from less common/difficult languages – PLM, Assembly) • FORTRAN not converted

  19. Migration Phases • Migration Phase II – 1997-1998 • ICCP for standards-based communications with: • PJM • PEPCO to BGE (planned merger) • Ranger Data Acquisition Server • Compaq Alpha hardware and Unix operating system • Bow Software Protocol Emulations

  20. Migration Phases • Migration Phase II – (cont.) • Addition of PI Historian Data Repositories • Upgraded DTS • Increased Database Sizing • Via System Master Parameters

  21. Migration Phases • Migration Phase III – 1999 – 2000 • Workstation Based Graphical User Interface • ODBC Interface Into EMS • NT Based Historian • Study Mode State Estimator – Uses Historian Data for Studies • DNP Protocol

  22. Migration Phases • Migration Phase III (cont.) • Event Storage and Retrieval • Updated Software Tools to Improve Maintenance and Support Environment

  23. Migration Phases • Migration Phase IV – 2001-2002 • (currently in progress) • Increase DB Sizing (1.5 x current) • Naming size increases • DNP Protocol Converter (Rockwell 5020 to DNP) • Transfer Existing RTU to RDAS • Graphical Data Engineering Tool • CIM Based

  24. Migration Phases • Migration Phase IV – (cont.) • Facilities and Support Systems • Console Voice Equipment (integrates PEPCO’s radio and telephone requirements) • Upgrade/Life Extension for Critical Power (UPS) and HVAC

  25. Migration Phases • More to Come? • Phase V – Commercial Display Generation Software • Phase VI – Upgrade EMS Application Processors, storage devices, printers, Bow-Tie Equipment, LAN I/F • Phase VII – SCADA System • Phase VIII – Advanced Apps. • These phases are currently under review

  26. EMS Migration • Related EMS Enhancement Efforts

  27. Related EMS Enhancement Efforts • RTU Protocol Conversion for existing RTUs • Outage Management System/EMS Interface – using ICCP • Source Data Management System – to improve data management process • System Security Enhancements

  28. Related EMS Enhancement Efforts • PEPCO Substation Automation Initiatives: • Increased data from smart relays and Substation Automation systems (4 kV, 13 kV, 69 kV, 230 kV substations) • VAR Dispatch – using feeder capacitors.

  29. Related EMS Enhancement Efforts • PEPCO Distribution Automation Initiatives: • Feeder sectionalization using fault detectors and Motor Operated Disconnects • 69 kV MODs • 13 kV MODs • Utilinet Spread Spectrum Radios

  30. EMS Migration • Future Migration Phases

  31. Future Migration Phases • Migration of Advanced Applications to support: • New Business Needs • New ISO Support Requirements • New Corporate Information Needs • Corporate Reorganizations and Industry Restructuring

  32. EMS Migration • Long-Range Plan & Update Process

  33. Long-Range Plan and Update Process • PEPCO is currently reviewing the Long-Range Migration Plan • Looking at current operational and business needs • Investigating current technology • Assessing impacts of restructuring • To properly align the next migration phases with the overall long-term direction

  34. Long-Range Plan and Update Process • Goal is to provide an updated 10 Year Forecast for planning purposes. • Also to more clearly define the near-term needs and associated migration projects.

  35. EMS Migration • Challenges for the Future

  36. Challenges for the Future • Distribution Operations Optimization • Fault detection and automated feeder reconfiguration • Other distribution functions • Additional Expansion of Distribution Functional and Data Requirements • Smart Relays, MODs, etc.

  37. Challenges for the Future • Integration with Corporate Systems • Corporate-wide Data Availability • For Maintenance Monitoring System • Enterprise Application Integration (EAI) Environment

  38. EMS Migration Questions and Comments?

  39. EMS Migration • Thank You!

More Related