1 / 8

WMIC RTO Seams Task Force – Congestion Management

WMIC RTO Seams Task Force – Congestion Management. Wally Gibson Northwest Power Planning Council CREPC – Seattle, Washington November 1, 2001. Task. Examine the seams interactions of congestion management approaches of three western RTOs Perspective: single west-wide market

moeshe
Télécharger la présentation

WMIC RTO Seams Task Force – Congestion Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WMIC RTO Seams Task Force – Congestion Management Wally Gibson Northwest Power Planning Council CREPC – Seattle, Washington November 1, 2001

  2. Task • Examine the seams interactions of congestion management approaches of three western RTOs • Perspective: single west-wide market • Describe the results and implications, report back to RTOs for further action • Not intended as inter-RTO negotiating forum

  3. Current Status • First public working draft of report – September 24 • Uncertainty immediately following: • DSTAR to WestConnect transition • RTO West decision to look in depth at alternative approach before making final decisions • Further work on paper postponed till matters sort out enough to work through the seams implications • Preliminary implications in paper, but likely to be different with different approach in RTO West • WestConnect mostly unchanged from DSTAR

  4. Examples Examined • Example transactions: • McNary to Phoenix • Phoenix to Northern California • Several time frames: • Forward market, forward market with curtailment, real time • Picked to involve • Major loop flow • Different congestion approaches in originating RTOs • Direct path either passing or not passing through third RTO • Implications for phase shifter operation

  5. 100 McNary to Phoenix 100 72 7 1 3 13 4 77 100

  6. 100 Phoenix to N. California 16 4 2 100 3 9 2 84 100

  7. Assumptions and Scenarios • Congestion management approach • DSTAR/WestConnect - contract path physical rights • RTOW - flow-based physical rights (likely to change) • CAISO - injections-withdrawals, adjustment bids, hybrid FTRs • Commercial representation of power flow on grid • Open loop – Flow-based within individual RTO only • Closed loop – Flow-based across entire western grid • Contract path – Not flow-based • Not address DC Intertie

  8. Issues Raised so Far • Some combinations lead to phantom congestion day ahead and unused capacity in real time • Choice of open- or closed-loop grid representations can affect ability to use phase shifters as forward market tools instead of using them to fix real-time loop flow problems • Generator redispatch bidding across RTO boundaries needs to be addressed • Security issues need to be highlighted in next round of paper • Paper posted at www.wrta.net/seamsmeeting.htm (September 24 meeting materials #1)

More Related