1 / 23

Monitoring and reporting project status Chapter 10, pages 317-342

Monitoring and reporting project status Chapter 10, pages 317-342. CSSE 372 20.Oct.2008. Outline. Control vs. risk Other kinds of reporting EV. Why do we need to monitor progress?. 70% of projects are: Over budget Behind schedule

nami
Télécharger la présentation

Monitoring and reporting project status Chapter 10, pages 317-342

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Monitoring and reporting project statusChapter 10, pages 317-342 CSSE 372 20.Oct.2008

  2. Outline • Control vs. risk • Other kinds of reporting • EV

  3. Why do we need to monitor progress? • 70% of projects are: • Over budget • Behind schedule • 52% of all projects finish at 189% of their initial budget • Average of 16% of SW projects are on-time and budget Source: The Standish Group

  4. How and What to Update? • Determine a set period of time and day of week • Report actual work accomplished during this period • Report start and finish dates • Report days of duration accomplished and remaining • Report resource effort • Report percent complete

  5. Types of progress reporting • Current period reports • Cumulative reports • Exception reports • Stoplight reports • Variance reports • Numerical • Graphical

  6. Milestone trend charts

  7. EVA • Earned Value Analysis (EVA) is: • an industry standard way to: • measure a project’s progress, • forecast its completion date and final cost, and • provide schedule and budget variances along the way.

  8. Baseline vs. actual cost curve

  9. Let’s talk terms • BCWS - Budgeted Cost of Work Scheduled • ACWP - Actual Cost of Work Performed • BCWP - Budgeted Cost of Work Performed

  10. Variance (EV – PV) • Positive • Indicates ahead of schedule or less cost than planned • May not always be good • Negative • Indicates behind schedule or more cost than planned • May not always be bad

  11. Full story http://evm.nasa.gov/images/key_data.gif

  12. Performance indices • Schedule Performance Index • SPI = BCWP/ BCWS • Cost Performance Index • CPI = BCWP/ ACWP

  13. Let’s do an example… PROJECT STATUS: Make 1000 widgets over 50 days (20 per day) INPUT: Total Expected Output = 1000 INPUT: Budgeted Unit Cost = $.50 Total Project Budget is 1000 x $.50 = $500. http://www.earnedvalueanalysis.com/index.cfm?nextpage=example

  14. EV Input BCWS: How much did we expect to pay for the work that was scheduled? Total Project Days = 10 Unit Production Per Day = 20 widgets/day Budgeted Unit Cost = $.50/widget BCWS = 10 days x 20 widgets/day x $.50/widget budget = $100

  15. EV Input BCWP: How much did we expect to pay for the work that was actually done? Actual Current Output = 150 Budgeted Unit Cost = $.50/widget BCWP = 150 widgets x $.50/widget budgeted = $75

  16. EV Input ACWP: What was the actual cost of the work that was completed? Actual Current Output = 150 Actual Unit Cost = $.60/widget ACWP = 150 widgets x $.60/widget actual = $90

  17. EV Analysis SV: Schedule Variance = BCWP – BCWS The Question: Are we ahead or behind production schedule? SV = BCWP – BCWS = $75 - $100 = -$25

  18. EV Analysis SPI: Schedule Performance Index = BCWP/BCWS The Question: How far ahead or behind schedule are we? SPI = BCWP/BCWS = 75/100 = 0.75 (LT 1, so behind schedule)

  19. EV Analysis CV: Cost Variance is measured as follows: If BCWP > ACWP, the project is UNDER budget! If BCWP < ACWP, the project is OVER budget! The Question: Are we on or off budget? CV = BCWP - ACWP = $75 - $90 = -$15 (negative means over budget)

  20. EV Analysis CPI: Cost Performance Index The Question: How far on or off budget are we? CPI = BCWP / ACWP = 75/90 = 0.8333 (less than 1 means over budget)

  21. Project forecast EAC: Estimate at Completion Method 1: BCWP at a point + Estimates to completion. Method 2: The ratio of BAC / CPI. Method 3: (Wilkens) [(BAC - BCWP)/CPI] + ACWP The Question: At the rate going, how much will all of this cost? This is a SIMPLIFIED estimate of EAC      EAC = BAC / CPI = $500 / 0.8333 = $600

  22. Questions?

More Related