SlideServe
Menu
Préférences
© SlideServe · v2026

WECC Standards Update: Key Developments in Reliability and Security (June 2014)

neil-richardson avatar
11 diapositives · 249 Views · Nov 02, 2014

This document presents an overview of recent developments in the WECC Regional Reliability Standards as discussed in the Joint Guidance Committee meeting on June 5, 2014, in Salt Lake City, UT. Key topics include the FERC's approval of IRO-006-WECC-2, ongoing projects in generator validation and energy product codes, and the NERC Physical Security Standard. The presentation highlights the implications for transmission operators and the importance of adhering to upcoming deadlines for assessments and initial risk assessments.

WECC Standards Update: Key Developments in Reliability and Security (June 2014) - slide 1
01 / 11WECC Standards Update: Key Developments in Reliability and Security (June 2014)
1 / 17

Télécharger la présentation

WECC Standards Update: Key Developments in Reliability and Security (June 2014)
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Steve RueckertDirector of Standards Standards Update June 5, 2014 Joint Guidance Committee Meeting Salt Lake City, UT

  2. Overview • WECC Regional Reliability Standards • Recent FERC Approval • Current Projects • NERC Projects

  3. Recent FERC ApprovalIRO-006-WECC-2 • FERC issued a Letter Order Approving IRO-006-WECC-2 on May 13, 2014 • Effective July 1, 2014 • No impact on BA or RC requirements • Updated to remove the reference to a specific WECC Unscheduled Flow Mitigation Plan and instead refer to the currently effective Plan regardless of which one it is

  4. Current WECC Regional Standards Activities WECC-0101 - Generator Validation Policy Conversion • Proposal to lower the applicable facility thresholds for generator testing and validation identified in recently approved NERC MOD standards • Proposal to modify the periodicity • Would become a Regional Variance to the NERC Standards • Would reflect current WECC Policy

  5. Current WECC Regional Standards Activities WECC-0105 – P81 Revisions • VAR-002-WECC-1 (AVR) • VAR-501-WECC-1 (PSS) • Proposing to delete R2 in both Standards and move it to the Measure for R1 • Ballot Pool Formation 5/28 – 6/19 • Ballot Window 6/25 – 7/18

  6. Current WECC Regional Standards Activities WECC-0106 – Energy Product Codes • INT-018-WECC-RBP-1 • No changes to the Definitions of the Codes • No changes to the requirement to use the Codes • Formatting • Moved actual definitions to the WECC Glossary • Ballot Pool Formation 5/28 – 6/19 • Ballot Window 6/25 – 7/18

  7. Current WECC Regional Standards Activities WECC-0107 – PSS Design and Performance • Originated from an RPIC assignment to review documents for appropriate categorization • WECC CWG identified several PSS documents that are related to reliability and should be considered for inclusion in regional reliability standards • The Drafting Team is still working on the first draft

  8. NERC Physical Security StandardImpact on the Western Interconnection • 84 WECC TOs will have to conduct an assessment (Requirements R1 and R2) on approximately 687 substations • 338 500 kV • 81 345 kV • 268 230 kV • Unknown without the assessments how many substations, if rendered inoperable, will result in widespread instability, uncontrolled separation, or Cascading

  9. NERC Physical Security StandardNext Steps • NERC Board of Trustees Adopted the Standard on May 13 • NERC filed the Standard with FERC on May 23 • Expectation is that FERC will act quickly

  10. Physical Security StandardBE AWARE • The initial risk assessment required by R1 must be completed on or before the effective date of the standard

  11. Questions?